Documents filed on behalf of the Attorney General alleges that Consultancy Services under the Saglemi Housing project were awarded three times, costing the taxpayer an estimated $13m.
First, in April 2013, the Architectural & Engineering Services Limited (AES Ltd), which had the consultancy contract, decided to subcontract its Services to Vito-Hugo-Coordenacaoe Gesto De Projectos (VHM) for a period of 24 months.
A maximum amount of $2.9m was to be paid VHM, while AESL was to take not more than $2m.
In April 2015, while VHM and AESL are said to have been providing the said Services, the Ministry of Works and Housing is alleged to have entered into another contract for consultancy services with Ridge Management Solutions DEC-LLL (RMS).
RMS was represented by its director and majority shareholder, Nouvi Tettey Angelo. This was to span a period of three months at a contract sum of $5.6m.
This was at a time RMS was not registered in Ghana as a company. However, the AG’s office says its investigations revealed Mr Angelo is also a Director of VHM awarded the same services two years earlier.
In August of 2016, then Minister of Works and Housing Kwaku Agyeman-Mensah is alleged to have entered into yet another consultancy agreement with RMS, this time christened “marketing implementation services” for a sum of $2.5m.
The AG notes that all this while, these Consultancy Services were being performed by AESL and VHM as per the agreement signed in 2013.
This the AG claims had been extended at various times by Mr Agyeman-Mensah and Ziblim Yakubu, former Chief Director at the Ministry.
The AG concludes that further payments were made to AESL, VHM and RMS far more than the $5m stated as consultancy fees under the original Housing project agreement.
These payments the AG claims were without any evidence of work done contrary to the contract's requirement.
Former Ministers of Works and Housing, Collins Dauda and Kwaku Agyeman-Mensah, former Chief Director Ziblim Yakubu and two others are facing 52 charges for various roles said to have caused the state to lose money it borrowed to construct 5,000 housing units. Only 668 units are said to have been completed, with the AG describing them as “not habitable”.
Latest Stories
-
Spanish Gastronomic and Trade Exhibition “Taste Spain” returns on June 18
10 minutes -
Businesses urged to discover new markets, build sustainable brands
21 minutes -
Free agent Tariq Lamptey resumes training after ACL injury setback
22 minutes -
Today’s Front pages: Thursday, June 4, 2026
25 minutes -
‘Interco’ should build networks, not violence – Pinkberry CEO
28 minutes -
Cedi’s pressure to persist in June 2026; one dollar equals GH¢12.30  at forex bureaus
33 minutes -
Black Stars touch down in USA ahead of 2026 World Cup
36 minutes -
“I come from a very privileged and educated background” – Pinkberry, Burger King CEO reveals
41 minutes -
I turned down a NASA opportunity – Pinkberry CEO’s bold career shift
46 minutes -
Ecobank Group shareholders approve $40m dividend payment as 2025 results confirm strength of GTR strategy
48 minutes -
GSE boss Abena Amoah named chair of ICMA Regional Committee
1 hour -
They were born with twisted feet. They learned to walk
1 hour -
Adenta: GNFS ends dramatic rescue operation after building collapse; 4 survivors pulled from rubble
1 hour -
Government releases 85% of Agriculture Ministry’s 2026 Budget
1 hour -
UMB appoints Victoria Esinam Attipoe as Branch Network Head for its Greater Accra Division
2 hours