Grande Côte Opérations (GCO), a subsidiary of the Eramet Group, has signed a Memorandum of Understanding with CrossBoundary Energy to construct a 13 MW hybrid solar power station with an 8 MW battery storage.
Dedicated to the Diogo industrial site (north-western Senegal) for the production of mineral sands, this solar power station is scheduled to be commissioned in early 2023. Its renewable energy will help improve GCO's carbon footprint and reinforce its ISO 50001 approach.
This is a first that reinforces the company's commitment to the climate, in line with that of the Eramet Group, which has set itself the objective (Science Based Targets - SBT) of reducing the CO2 emissions (scope 1 and 2) of its activities by 40% by 2035 (based on 2019).
CrossBoundary Energy will design, build and operate the plant, which will generate all the renewable energy for GCO through a 15-year distribution contract.
Guillaume Kurek, CEO of Grande Côte Operations, said, "The clean, renewable and available energy from this hybrid plant will contribute to GCO's environmental and economic performance. In addition, the environmental value of the titanium and zircon raw materials that GCO produces will be positively impacted.
"This concrete commitment to low-carbon energy reflects the values and ambition of the GCO and Eramet Group teams to provide solutions to the vital climate challenge and the living well together”.
Matthew Fredericks, Director of Business Development for Mining, CrossBoundary Energy, said, “We are excited to announce this MOU as the start of our long-term partnership with Grande Côte Operations Mineral Sands.
"CrossBoundary Energy’s flexible, fast, all-equity funded approach and implementation partner juwi’s international track record in hybrid power system construction for mines are the ideal combinations to deliver this complex project. We look forward to getting to work alongside GCO’s team on the next phase.”
Latest Stories
-
Asiedu Nketiah says he will declare presidential ambition ‘when the time is up’
50 minutes -
You cannot hide your ambition and expect people to vote for you – Asiedu Nketiah’s 2028 Message
1 hour -
I won’t declare NDC Chairmanship re-election bid before internal elections – Asiedu Nketia
1 hour -
I have never ruled any position out – Asiedu Nketiah keeps presidential ambition alive
2 hours -
Ghana needs fixed campaign periods to reduce election distractions – Asiedu Nketia
2 hours -
Asiedu Nketiah brushes off Haruna Iddrissu’s ‘proper Thank-You Tour’ jab
2 hours -
I’d be a stupid Chairman if I sat idle – Asiedu Nketiah defends Thank-You Tour
2 hours -
Asiedu Nketia calls for state funding of party primaries, says 2014 one-member-one-vote exercise cost GH¢14m
2 hours -
I don’t need a Thank-You Tour to sell myself – Asiedu Nketiah rejects presidential agenda claims
2 hours -
One year is enough to replace delegates system with one-member-one-vote – Asiedu Nketia
3 hours -
Mahama addresses the joint sitting of Jamaican Lower/Upper Houses in Kingston
3 hours -
Mahama pays tribute to Marcus Mosiah Garvey in Jamaica
3 hours -
Magistrate court remands two over alleged murder of suspected burglar
3 hours -
GoldBod hasn’t lost GHS200m; Dominic Bonsu was never my bodyguard — Sammy Gyamfi rebukes Kofi Bentil
3 hours -
Why should gov’t choose 3 candidates for us? – John Darko rejects MMDCE selection model
4 hours