
Audio By Carbonatix
Chief of Kuntenanse in the Bosomtwe District of the Ashanti Region, Barima Amankwaah Adunan Ababio, has urged President Akufo-Addo to ensure construction of the Kumasi-Bosomtwe road continues after his visit.
Construction of the road stalls intermittently since it started in 2018 because the contractor abandons the road.
Barima Amankwaah Adunan Ababio attested to the return of the contractor in the past few days. But he said unless the necessary action is taken, the contractor, Kofi Job Construction, will be sacked from site.
"You awarded the road for construction in 2018, the contractor came in April 2019. The contractor comes on site for about a week and packs out. Today, I have seen his trucks parked along the road. I think it is because of the President's visit, he will soon park out", he told the President".
On the second day of the President's visit to the Ashanti Region, residents of Atwima Boko expressed their dissatisfaction over the continued stalling of the Kwadaso-Trabuom road project.

On the third day of the President's visit, when works on the Bosomtwe Road was inspected, construction trucks numbering about 20, were seen lined up on the road, a sign of active work on site.
The road is largely not tarred, making it dusty, thus making it challenging for businesses to operate.
Due to the deplorable state of the road, some residents have complained about respiratory ailments. It is almost not motorable during the rainy season. Also, bridges on the road are halfway complete, making usage difficult.

President Akufo-Addo in response to the Chief's request explained that his government has made massive investments in road development in Ashanti Region.
He however acknowledged that financing these roads is a major challenge his government is facing.
"If you start every project from point zero and make progress to point 4, it is difficult for people to notice. I came to meet point zero that's why you are still complaining. We can't fix all at once due to financing but before I leave the presidency the road will be done", the President said.

The road is largely not tarred, making it dusty. It is almost not motorable in the rainy season. Bridges on the road are half way complete, making usage difficult.
Businesses along the road are on the verge of collapse due to excessive dust. Residents claim many are developing respiratory illness.
The President also inspected the Kumasi Roads and Drainage Extension Project.
The 250-bed capacity hospital at Sewua is 95 percent complete. the contractors, Euroget D'Invest, are committed to handing over the site in November, 2021. They said access to utilities and poor road connection to the hospital hinder completion.
Latest Stories
-
CSOs raises alarm over contraceptive shortage as $500k UNFPA stock remains stuck at port
3 minutes -
Africa’s youth bulge a ‘defining moment’ that requires urgent action – NYA CEO Osman Ayariga
10 minutes -
No looming power crisis; Ghana’s electricity supply remains stable – Energy Ministry PRO insists
26 minutes -
Mahama should reset his stance on LGBTQ -Clinton Baffour
32 minutes -
Rising sachet water costs should spark a bigger conversation on plastic waste
35 minutes -
Two-week ceasefire takes effect as US and Iran prepare for talks in Pakistan
38 minutes -
Dr. Amoakohene debunks claims Sewua and other Agenda 111 hospitals are ready for operationalisation
46 minutes -
AMA rolls out new shift system for street sweepers to improve sanitation
50 minutes -
Focus on capacity, not connections in Damang lease decision – Paa Kwesi Schandorf
1 hour -
Teen defender Eric Mensah undergoes trial at Malaga CF after standout ROC Cup display
1 hour -
Journalism out loud: Why silence is no longer an option
1 hour -
NYA boss identifies unemployability as Africa’s core youth challenge
1 hour -
5,000 miners stranded in Ahafo-Ano North as alleged NAIMOS operatives take over site
1 hour -
GMTFcare rollout begins at Komfo Anokye Teaching Hospital to transform patient support
1 hour -
Leicester lose appeal against points deduction
1 hour