Works and Housing Minister Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024, with project coordinators and contractors to address delays plaguing the critical initiative.
"We've assessed how far the project is going and we've had several site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.

He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays.
Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval.

Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.

Addressing the Hurdles
The Minister outlined a series of measures to tackle these challenges. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up critical work areas.

On the financial front, Mr Oppong Nkrumah reassured contractors that government is actively working with Parliament to make available the outstanding funds, including the diverted $65 million.
A Race Against Time

While acknowledging the challenges, Mr Oppong Nkrumah emphasized the urgency of the completion of the GARID projects.
He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.
Latest Stories
-
KATH compelled to detain patients over medical bills, complains of costs and resource burdens
1 minute -
Gov’t begins construction of CATH Lab at KATH to curtail surging heart conditions
14 minutes -
High Court dismisses Gifty Oware’s application for Supreme Court referral
14 minutes -
Education Minister proposes ‘Our Day’ cultural wear in schools after Mahama’s fugu buzz
18 minutes -
Women’s FA Cup: Hasaacas draw Ampem Darkoa Ladies in quarterfinals as Jonina face Supreme Ladies
30 minutes -
Ghana’s food insecurity hits 38.1% as over 13m people face hunger risks- GSS
36 minutes -
Ghana holds strategic talks with Afreximbank on minerals sector development
36 minutes -
Cost of Azumah Nelson Sports Complex to be revealed after completion – NYA CEO
40 minutes -
Tetteh Quarshie Memorial Hospital records milestone with first dialysis procedure after 64 years
42 minutes -
Cape Coast Phase II Sea Defence project advances to protect coastal communities
44 minutes -
Macron urges Europe to start acting like world power
44 minutes -
Why Ghana should declare February 4 National Fugu Day
48 minutes -
Assessing the finance minister’s priorities one year on: prices and the cedi
54 minutes -
Azumah Nelson Sports Complex, other youth centre to be completed by end of 2026 – NYA CEO
1 hour -
Ghana leads discussions on responsible mining at Africa Mining Indaba
1 hour