Construction works on the Tema-Aflao highway resumed on April 7, 2025, after a 15-month suspension, but fresh concerns are emerging over delayed funding that could threaten the project’s smooth execution.
Contractor BHM International, responsible for the 17-kilometre stretch between the Kpone-Barrier and the Central University campus at Miotso, says the $105 million loan facility earmarked for the project has still not been reinstated.
Client Relations Manager at BHM International, Wisdom Adonoo, speaking to JoyNews after a visit to check progress of work warns that the longer the delay persists, the greater the risk of slowing down or even stalling progress which is scheduled for completion in 18 months.

“We are still waiting for the loan to be reinstated. In the meantime, we are working in good faith based on the minister’s assurance in April, and we are committed to delivering this project on time. But the longer the funds delay, the more difficult it becomes to execute the work as required by contract.”

A visit to the site shows significant improvements compared to five months ago. On the Tema-to-Aflao side, contractors have expanded the road by adding more lanes.

Most sections have already been filled and opened to traffic during peak hours, easing congestion that road users previously complained about.
On the Aflao-to-Accra side, excavation is still ongoing across several stretches, with heavy trucks and machinery actively at work.

BHM says the next phases include stabilisation, stone base pavement, asphalt, and pedestrian walkways, along with the completion of four planned flyovers, three of which already have structures erected.

Beyond funding, compensation for affected residents and traders remains a challenge. According to the Public Relations Officer Pastor Samson Allotey, out of 1,131 people identified for compensation, 842 have so far been paid, representing about 74.5%. Roughly half of those compensated have relocated to allow for construction, but the remaining yet to be compensated threatens work on section of the road.
“We urge government to expedite compensation for the remaining affected persons. Until payments are made and relocations completed, clearance for construction in some areas will remain an issue,” he said.
Latest Stories
-
Humour at its finest at Kumasi Comedy Show
2 minutes -
Police Christmas special operation: 101 suspects arrested in Greater Accra
26 minutes -
15 arrested after sporadic shootings at Ho central mosque
40 minutes -
GES condemns alleged theft of food supplies at Awaso STEM SHS
1 hour -
DopeNation electrifies crowd at Joy FM’s Party in the Park
1 hour -
Philip Ayesu emerges as the 2025 Achimota Champion after beating Percival Kwadjo Ampoma
1 hour -
Support your own – Mr P tells Ghanaian artistes
1 hour -
Ghana EXIM Bank develops 5-year export-led growth strategy to drive trade expansion
2 hours -
Big Smiles, Bigger Bounces: Kids take over the fun at the Joy Party in the Park
2 hours -
Joy FM Party in the Park 2025: Kwabena Kwabena takes centre stage
3 hours -
Ghana-Nigeria cyber-fraud network dupes over 200 victims of $400,000
3 hours -
Tackling terrorism requires jobs and anti-corruption drive, not strikes alone – Nigerian security analyst
3 hours -
Terror attacks in Nigeria affect all faiths, not only Christians – Security analyst
3 hours -
$120,000 stolen from Ghanaian financial institution by hackers – INTERPOL
3 hours -
Modern security management defined by trust – IGP
3 hours