The Minister for Works, Housing and Water Resources, Ahmed Ibrahim, has called for a review of the proposed one-year construction period for planned works on the Kaneshie–Pamprom to First Light road stretch, insisting that efforts must be made to complete the project within a shorter period.
He said the government was concerned about the significant inconvenience and traffic disruptions. The closure of about 1.5 kilometres of the busy stretch would cause motorists and residents.
The Minister made the remarks after leading officials on a site inspection to assess the planned works under the GARID project, following a presidential press conference and the commencement of public sensitisation on the proposed road closure.
The project would involve the removal of the entire asphalt surface on the affected stretch to allow for major drainage and engineering works aimed at addressing persistent flooding in the area.
Mr Ibrahim explained that although the road appeared normal on the surface, extensive engineering works were required beneath it, including improvements to drainage infrastructure.
He said the planned closure would be carried out in phases, with extensive public education and awareness campaigns to guide motorists on alternative routes.
However, the Minister stressed that before full-scale construction began, key stakeholders, including the Ministers for Roads and Highways, Finance and National Security, must be adequately briefed on the potential impact of the project.
He said a thorough assessment was needed to determine whether alternative roads could accommodate the thousands of vehicles that use the Kaneshie–First Light stretch daily.
“Even when it is in good shape, there is traffic. So before you touch it, we should know the number of cars that move on this stretch and whether the alternative routes can take the vehicular traffic that will be diverted,” he added.
Mr Ibrahim also called on the contractor to demonstrate readiness and provide a clear work plan, including measures to speed up construction.
While the current completion period is estimated at one year, the Minister said the government was exploring the possibility of reducing it to between six and nine months.
He clarified that a test run of the road closure would still be conducted to assess its impact on traffic flow but said the duration of the construction work remained a major concern.
Mr Ibrahim said that the government would not allow the travelling public to endure unnecessary hardship due to delays in completing the project, and that if he was not convinced, the project would not commence.
He said the contractor must work closely with the government to identify any additional support or resources required to ensure the project was completed on schedule.
Latest Stories
-
GTP, Woodin enter new era as TexStyles Ghana comes under local ownership
2 minutes -
NSMQ 2026: St. Augustine’s College march into third straight final, beat Prempeh and Pope John
2 minutes -
Sharpeville massacre survivors start legal fight for justice in South Africa
4 minutes -
Chief Justice has ‘worn a political jersey’ – Tampuli calls for resignation
27 minutes -
Local Government Service partners Celltel to accelerate digital transformation
31 minutes -
CJ’s role includes building working relationships with state institutions — NDC’s Hamza Suhuyini
32 minutes -
Police intercept vehicle carrying suspected contraband at Jema
33 minutes -
BOSTenergies pays first-ever GH¢34.2m dividend to government
34 minutes -
Accra–Kumasi Expressway: 170km of corridor cleared, only 6km remains – GAF
42 minutes -
Maritime security and naval cooperation in a changing international order
44 minutes -
Over 8,000 candidates compete for just 800 places at Aburi Girls’ SHS – CSSPS
44 minutes -
‘Did he lie? I don’t see anything political about Chief Justice’s comments’ – Franklin Cudjoe
47 minutes -
NDC’s Hamza Suhuyini accuses NPP of hypocrisy over Chief Justice’s remarks
48 minutes -
Sekondi-Takoradi records 152 new HIV infections in 2025
58 minutes -
Agbodza orders Wa-Bulenga road contractor back to site
59 minutes