Ghana is set to open sub-Saharan Africa’s first liquefied natural gas-to-power project as it moves to position itself as a hub for the cleaner and cheaper fuel in the region.
LNG-to-power projects have been booming from Asian to Latin American in recent years as they allow nations to switch from dirtier fossil fuels to keep the lights on. And for sellers, integrated LNG-to-power provides a guaranteed outlet for the fuel.
Tema LNG Terminal Co. received the floating regasification unit from Jiangnan, China on Wednesday, paving the way for the supply of 1.7 million tons of natural gas per year for power generation sometime this quarter, Edmund Agyeman-Duah, project manager at the company, said.
The company, backed by Helios Investment Partners and Africa Infrastructure Investment Managers, began building the $350 million project about two years ago. “Ghana can now start to service the rest of the region with fuel that is continuously growing in popularity because of the cost and the significant environmental benefits it provides,” Agyeman-Duah said.
Lower Emissions
On a lifecycle basis, LNG emits around half the greenhouse gas emissions that coal does when burnt to generate electricity, and compared to a typical new coal plant, natural gas emits 50 to 60% less carbon dioxide when combusted in a new efficient natural gas power plant, according to the International Group of Liquefied Natural Gas Importers.
For a country with 30 million people, Ghana’s electricity consumption has grown alongside its economy, but it remains lower than the average per capita consumption of Sub-Saharan Africa and far below that of developed countries. For comparison, a U.S. resident consumes more than 30 times as much electricity as a Ghanaian resident, according to World Bank data.
“The completion of the Tema LNG facility will be significant for Ghana andand the wider West African sub-region because it will mean less dependency on the West African Gas Pipeline - which hasn’t always proved reliable,” Kissy Agyeman-Togobo, a partner and analyst at Songhai Advisory Group Ltd., said by phone from Accra, Ghana’s capital.
Tema LNG Terminal is getting its gas under a long-term contract with Royal Dutch Shell Plc, said Agyeman-Duah, who isn’t related to the analyst. State-owned Ghana National Petroleum Corp. is currently the mandatory off-taker who will receive regasified LNG to fuel plants in the Tema power and industrial enclave.
“There’s quite a bit of suppressed demand in the system,” he said. “There are a lot of industrial customers who work off-grid because of the interruptions they suffer in power supply.” The company has given Spain’s Reganosa Servicios SL the contract for the operation and maintenance of the unit and associated 6 kilometer (3.7 miles) gas pipeline, it said in a statement.
The project was financed with a combination of equity and debt from a consortium of international banks, according to Agyeman-Duah, and its processed LNG is expected to be 30%-35% cheaper than heavy fuel oil, he said.
Latest Stories
-
NPP accuses government of selective justice, warns against interference in Sedina Tamakloe’s sentence
1 minute -
Ashaiman Police arrest two suspects over separate armed robbery attacks
10 minutes -
Port charges hindering access to donated medicines, cancer charity warns
21 minutes -
See the areas that will be affected by ECG’s planned maintenance on Tuesday
28 minutes -
Mahama’s lean government claim misleading when full appointments are considered – Jinapor
34 minutes -
India temporarily bans Telegram over exam paper leak concerns
44 minutes -
The COCOBOD files: A Compendium
45 minutes -
Ghana records at least 13 university student deaths since 2024 as campus safety fears mount
1 hour -
Photos: Mahama oversees 48th Ceremonial Changing of the Guard at Accra Presidency
1 hour -
Tesano Gardens Junction residents call for traffic lights after fatal motorbike crash
1 hour -
Feed Ghana Programme to improve crop productivity through soil testing and efficient fertiliser use
2 hours -
NAPO urges politicians to make realistic promises to avoid public disappointment
2 hours -
The Hyena, the leopard, and the silence of Nunyãdume
2 hours -
Ga South MCE says illegal Amanfrom waste dump operators are being prosecuted
2 hours -
Audit flags irregularities in Heal Komfo Anokye Project amid dispute over control of funds
2 hours