Audio By Carbonatix
Nana Addo Dankwa Akufo-Addo, has inspected ongoing work on the construction of a 500-bed military hospital and work on the construction of Phase II of the Kumasi Airport project.
President Akufo-Addo’s first port of call on day one of his 3-day working visit of the Ashanti Region was the Kumasi Airport.
It will be recalled that on 6th June 2018, the President cut the sod for work to commence on phase Ii of the Kumasi Airport Project, where he explained that “the expansion of this airport is a critical part of government’s vision to expand the frontiers of the aviation industry in the country, and to realise the dream of making Ghana an aviation hub in West Africa.”
The project encompasses the extension of the current length of the runway by 319 metres, i.e. from 1,981 metres to 2,300 metres; construction of a new terminal building, with the capacity to handle one million passengers per year; construction of an apron area and related taxiway; and the undertaking of ancillary works.
The project coordinator told President Akufo-Addo that permanent works on the terminal building are progressing steadily, and the installation of the steel superstructure also progressed as scheduled.
Pavement works for access road construction, he added, are in progress, together with the construction of storm drains network in the terminal area, with the revised completion date for the project is August 2021.
The President also visited the site of the construction of the 500-bed Military at Afari, in Atwima Nwabiagya South constituency.
It will also be recalled that former President Kufuor granted Executive Approval for the project on 4th November 2008, which included the construction of a 250 Bed Regional Hospital; 160 Bed Regional Hospital; 100 Bed Municipal Hospital; and five (5) 60 Bed District Hospitals in the early part of 2008 at a total cost USD519,000,000.00.
Parliamentary approval for the project was given on 13th November 2008. Eight (8) years later, in December 2016, the related Tax Exemptions and other imposts including those for import duties, VAT, NHIL, ECOWAS Levy, withholding tax, fees and charges on onshore and offshore purchases of specific project materials and equipment were eventually approved by Parliament, with concurrence letter from the Ministry of Finance in January 2017 paving the way for the project to commence.
President Akufo-Addo received the assurance of the CEO of Euroget de Invest, contractors for the project that the 500-bed military hospital will be completed by December this year.
Latest Stories
-
Hundreds of cats stolen for food in Vietnam rescued by police, welfare group says
2 hours -
Brazil convicts Jair Bolsonaro’s son of pursuing US help in father’s legal battle
2 hours -
Musk’s SpaceX overtakes Amazon to become world’s fifth most valuable firm
2 hours -
2026 World Cup: What would Ghana lose without Thomas Partey against Panama?
2 hours -
German broadcaster removes TV intro after Elon Musk takes legal action
2 hours -
Haaland scored twice on World Cup debut as Norway beat Iraq
2 hours -
Spurs agree £52m Van Hecke deal with Brighton
2 hours -
World Cup: The VAR call that dumbfounded the world’s best referees
3 hours -
World Cup: Snakes on a train (ing pitch)
3 hours -
Olise is your man of the match in France World Cup opener
3 hours -
Partey misled Canadian officials over previous arrest
3 hours -
Kylian Mbappe France’s all-time top scorer in win over Senegal
3 hours -
Confidence high as Vice President visits Black Stars ahead of Panama showdown
3 hours -
BECE 2026: Five important steps JHS graduates should take before starting SHS
3 hours -
2026 World Cup: Ghana fails in bid to have Partey’s Canada visa denial overturned
4 hours