AngloGold Ashanti is continuing underground development and important work related to the Obuasi Redevelopment Project, while a detailed review of the mine plan is conducted in the coming months.
Work has resumed in the ODD Decline and in several development headings. Diamond drilling, service functions and underground construction, among other activities, have also resumed.
Underground stoping activities, halted after a fall-of-ground incident on May 18, remain suspended pending the conclusion of the review and implementation of recommendations from an investigation into the incident.
AngloGold Ashanti estimates mining could restart by year-end, with a ramp-up to previously planned production levels through the course of 2022.
“We are focused on understanding and dealing with the current issues and resuming the ramp-up as soon as possible,” said Eric Asubonteng, Managing Director of Obuasi Gold Mine.
“Obuasi remains an excellent asset and an important one for us, as a company, for the community and for Ghana as a whole.”
AngloGold Ashanti remains firmly committed to the Obuasi Redevelopment Project, which will revive one of the world’s largest gold ore bodies and create a modern, mechanized mining operation over more than 20 years.
Employees and contractors will be engaged in the ongoing project development in the coming months, while AngloGold Ashanti will use the production stoppage to continue to train and develop skills of the workforce ahead of the restart.
As the investigation progresses and the assessment of working places advances, the Company will provide an update on the resumption of additional mining fronts.
“We remain committed as ever to responsibly operating this important ore body for the benefit of all stakeholders,” Asubonteng said.
“Obuasi has a long future ahead of it. It is important that we proceed deliberately and carefully as we complete our programme of checks and balances in each mining section.”
Prior to the suspension of underground mining activities at Obuasi, the mine produced 85,000oz in the first half of 2021 at a total cash cost of $999/oz and an All-in Sustaining Cost of $1,316/oz.
Latest Stories
-
Two dead, one critically injured in domestic fire at Kodjonya
2 minutes -
No start date yet for Ghana–Dangote fuel deal — Gov’t
8 minutes -
GWL attributes Kokomlemle water crises to rationing, localised faults after JoyNews report
12 minutes -
Open letter to Ibrahim Mahama
31 minutes -
More UK troops to be sent to Middle East, defence secretary announces
39 minutes -
GMet warns of incoming rainstorm, flood risk across parts of Ghana
1 hour -
Mahama, NDC have abandoned anti-LGBTQ Bill after weaponising it to win power – Ntim Fordjour
1 hour -
Police arrest suspect over murder at Soronko Farms
1 hour -
The attack on Ghanaian traders in Burkina Faso and the blame game: Why Hybrid Security Governance holds the key (I)
1 hour -
TaxForGalamey: Stop taxing galamsey immediately or face sanctions – Gov’t cautions MMDCEs
2 hours -
FNB Ghana strengthens balance sheet with higher earnings and improved asset quality
2 hours -
Stakeholders call for stronger action to advance women’s economic empowerment at UKGCC–British High Commission IWD Event
2 hours -
Global Network of Export-Import Banks holds 6th exchange programme in Accra
2 hours -
Prudential Bank Ladies celebrate IWD with candid talk on Love, Life, and Livelihood
2 hours -
Kejetia Market now a ‘death trap’ – Federation of Kumasi Traders warns
2 hours