Audio By Carbonatix
The government of Ghana has been advised to consider the termination of the contract agreement between the National Youth Authority and New Case Construction Limited, for the construction of the Azumah Nelson Sports Complex.
In its latest audit, government's Entity Tender Committee reportedly discovered several breaches of the contract agreement, by New Case Construction Limited.
Speaking exclusively to JoySports, Chief Executive Officer of the NYA, Pius Enam Hadzide said the Authority was considering the recommendation.
''The Entity Tender Committee at its last meeting, advised that we consider the termination of the agreement because the contractor has no done some of the works that we believe should have been done by now.''
The Azumah Nelson Sports Complex, like all ten Youth Resource Centers across the country, was supposed to be completed within nine months of commissioning.
In August 2020, the facility was declared 78% complete by the project engineer, Paul Atanga.

Work was progressing steadily in 2019 until monies ceased coming
''We are 78% through with the work. When we started this work, there were unforeseen circumstances that we met, and as engineers when we meet a problem, we solve them before moving on.
''There is a drain that passes through the facility that discharges water from the Kaneshie township all the way to Odawna. It was passing through our VIP area, so we had to divert it so we don’t flood the industrial area.
''So that has been cleared. We are confident that we will finish the remaining 22% in the next few months, he told reporters during a site inspection.
However, work stalled on the project shortly after, following government's inability to pay contractors working on all ten Youth Resource Centers.
The NYA contends that it does not owe New Case Construction Limited, who are responsible for the project.
''So we are considering the termination (of the contract with New Case Construction Limited). And no, we do not owe them.'' he told JoySports.
Meanwhile, construction works on the nine other facilities have ceased due to a lack of funds.
The District Assembly's Common Fund have since July 2022, refused to release funds to the NYA.
Since the NYA is mainly funded by 5% of the District Assembly's Common Fund, the current situation has made it impossible to finance the project.
The $4million facility is expected to have an ICT Center, tennis and basketball courts, a FIFA standard sized pitch with seating capacity of 5,000 spectators and boxing gyms.
Latest Stories
-
Ghanaian delegation set for January 20, 2026 trip to Latvia in Nana Agyei case – Ablakwa
2 minutes -
Accra turns white as Dîner en Blanc delivers night of elegance and culture
2 hours -
War-torn Myanmar voting in widely criticised ‘sham’ election
4 hours -
Justice by guesswork is dangerous – Constitution Review Chair calls for data-driven court reforms
4 hours -
Justice delayed is justice denied, the system is failing litigants – Constitution Review Chair
5 hours -
Reform without data is a gamble – Constitution Review Chair warns against rushing Supreme Court changes
5 hours -
Rich and voiceless: How Putin has kept Russia’s billionaires on side in the war against Ukraine
5 hours -
Cruise ship hits reef on first trip since leaving passenger on island
6 hours -
UK restricts DR Congo visas over migrant return policy
6 hours -
Attack on Kyiv shows ‘Russia doesn’t want peace’, Zelensky says
6 hours -
Two dead in 50-vehicle pile up on Japan highway
6 hours -
Fearing deportation, Hondurans in the US send more cash home than ever before
6 hours -
New York blanketed in snow, sparking travel chaos
6 hours -
Creative Canvas 2025: Documenting Ghana’s creative year beyond the noise
10 hours -
We would have lost that game last season – Guardiola
10 hours
