Contractors say the Borteyman Sports Complex is nearing completion, with 87% of the work done ahead of the 2023 Africa Games.
This information was revealed during an extensive tour of the facility by the Local Organizing Committee, the African Union Sports Council (AUSC), and Chefs de Mission from countries on the continent.
The venue earmarked for the Games will host 21 sporting disciplines, including Swimming, Tennis, Badminton, and Volleyball.
When completed, the Borteyman facility is expected to have an aquatic center with a warm-up and competition pool that can seat up to 1000 people, as well as five tennis courts, among other amenities.
With five months remaining until the start of the games, the inspectors, led by the Coordinator for AUSC, Decius Chipande, expressed satisfaction with the work done.
"I think we are very happy with the progress that has been made so far, and the African Union is very grateful for the significant investment that the government of the Republic of Ghana has put into the construction of the facilities," Chipande said.
The Legon facility was also assessed by the inspectors and appeared to be far from completion. Tartan tracks for both the stadium and the warm-up field are yet to be designed, and other areas, such as the director’s box and the media tribune, remain unfinished.
Both facilities are expected to be ready and handed over in December, ahead of the Games, which start in March 2024.
Latest Stories
-
Church of Pentecost supports over 2,000 BECE candidates in Obuasi with career guidance seminar
9 minutes -
Brandon Asante and Coventry all but promoted to Premier League despite Sheffield Wednesday draw
31 minutes -
GPL 2025/26: Late Kwartemaa strike downs Hearts in Tema
37 minutes -
Ghana Faces Sierra Leone Moment as Prosecutorial Powers come under strain
47 minutes -
Don’t consume fish or seafood from Tema Shipyard until further notice – FDA warns
52 minutes -
Why volunteering might be Africa’s most underrated career accelerator
58 minutes -
ActionAid Ghana raises concern over gender gaps in Feed Ghana Programme
1 hour -
Windstorm wreaks havoc in Gushegu, displacing nearly 2,000 residents and damaging schools
1 hour -
Friends of Bridget Bonnie Marks her 35th birthday with donation to Kasseh Model Health Centre
2 hours -
From Ekumfi Kokodo to the Pulpit Stage: Essi Donkor’s gospel journey takes shape
2 hours -
Landfilling waste management creates no value, it’s an economic waste
2 hours -
Photos: Speaker Bagbin Commissions MPs constituency office under parliamentary decentralisation programme
3 hours -
Black Stars technical advisor Winfried Schäfer sacked as GFA shakes up backroom staff
3 hours -
Wenchi water project almost complete, critical to gov’t agenda – GWL MD
3 hours -
Anti-LGBTQ+ bill not part of government’s legislative agenda – Inusah Fuseini
3 hours