The Zongo and Inner City Development Minister has said the Kyebi, Madina and Walewale communities will have their Astro Turfs projects completed latest by mid-October.
Dr Mustapha Hamid told Joy News Monday that the contractors missed January 2019 completion date because of some changes to the original plan.
“We decided that there was the need to expand the spectators’ area from what we had previously planned for. Also, the early plans did not have changing rooms, which we thought was neccesary.
“In the case of some of the Astro Turfs like the one in Madina, we wanted to add a children’s playground as well as a basketball court to it, which has caused the delay on that project,” he said.
President Nana Akufo Addo in his 2018 State of the Nation Address reiterated his government's commitment to sports development, revealing that a number of football pitches are under construction across the country.
He said each constituency will have an astroturf and this will help produce the next generation of football stars.
“We are constructing a number of football pitches in the Zongos and across the rest of the country, to aid in the revival of colts football, which has been responsible for the production of talents like Abedi Pele and Tony Yeboah.”
A deal between Wembley Sports Construction Company Limited and Turkish company, HATKO, was agreed late 2017 to roll out the ‘One Constituency One Artificial Football Turf’ project.
The project began with the commencement of the construction of an artificial pitch in Madina which is expected to be completed by March.
Ashiaman, Krowoe, Okaikoi Central, Okaikoi North, Gomoa East, South Tongu, Ablekuma Central, Shai Osudoku are expected to be amongst the first constituencies to benefit from the project.
These projects have witnessed delays, but the Minister has assured that it was for a better reason.
“Due to the changes to the plans, we had to go through a fresh procurement process and seek funding from the Finance Ministry who in turn must send a request to parliament to approve the new budget for the project,” he explained.
Dr Mustapha Hamid says he is excited that his Ministry has gotten all the approvals needed and expects the contractors to get to their respective project sites within the week to continue work.
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
World Cup fever meets power anxiety: Ho residents plead for stable electricity
14 minutes -
Nii Lante Vanderpuye ready to contest NDC chairmanship if Asiedu Nketia steps aside
17 minutes -
Government to begin paying Free SHS suppliers’ arrears next week
20 minutes -
CSOs urge Supreme Court to uphold legality of Special Prosecutor’s office
23 minutes -
Mahama won’t shield Sedina Tamakloe from justice – Vanderpuye
26 minutes -
GMet proposes Authority status under new legislative framework
30 minutes -
Kpone Katamanso MCE condemns cattle invasion of school after viral video
33 minutes -
Speaker Bagbin calls for closer Parliament-Judiciary ties as Supreme Court marks 150 years
36 minutes -
World Blood Donor Day: Ghana celebrates humanity behind every drop of blood
39 minutes -
Mahama calls for new Ghana-EU partnership driven by trade, investment and industrialisation
42 minutes -
I’m not the president’s appointee; my allegiance is to MPs and Ghana – Speaker
45 minutes -
Fisheries Minister launches project to transform abandoned pits into fish farms
48 minutes -
Ghana-Canada investment forum to deepen economic cooperation
51 minutes -
Ashanti GNAT calls for calm over Nyinahin Catholic SHS teacher-student incident
55 minutes -
PBC workers call on Mahama to fulfil promise to revamp company
58 minutes