The Minister for Roads and Highways, Governs Kwame Agbodza, has disclosed that more than 90% of road contractors across the country are currently inactive, despite holding site possession.
This revelation raises serious concerns about the actual state of Ghana’s infrastructure, in contrast to the glowing assessments offered by the previous administration.
Speaking in an interview with Citi FM on 31 July, Mr Agbodza said a nationwide inspection undertaken shortly after assuming office exposed a stark disparity between reported progress and on-the-ground realities.
“More than 90% of road contractors are not on site,” he stated. “When I say they are not on site, I mean they are in possession of the site, but they are not doing any work.”
He clarified that while some contractors had commenced work and submitted interim payment certificates, a lack of timely disbursement of funds had forced many to halt operations.
“In many cases, to be fair to them, they have done some work, raised a certificate, and are expecting that some money be paid so they can continue. But once the money has not been repaid, some of them run out of cash and stay on site and do nothing, or abandon the site,” Mr Agbodza explained.
These comments echo the minister’s earlier remarks during the Government Accountability Series held at the Jubilee House on Wednesday, July 30.
At the event, he questioned the infrastructure claims made under the previous government and underscored the importance of relying on verifiable data to assess national development.
Mr Agbodza further assured that the current administration is committed to addressing funding constraints and ensuring contractors resume work on key infrastructure projects nationwide.
Latest Stories
-
MGL’s May Day Egg market ends in resounding success as crowds turn out for affordable eggs
27 minutes -
Energy expert advocates increased private-sector role in power distribution to tackle dumsor
33 minutes -
Tony Asare Writes: A clotted artery, by-passes and detours
37 minutes -
No road project cancelled under Mahama’s reset agenda — Roads Minister
42 minutes -
Mahama praises IGP Yohunu, hails intelligence-led policing at Krobo-Odumase commissioning
44 minutes -
“Energy situation is stable” – John Jinapor assures Ghanaians
46 minutes -
Ghana Tuna Association reaffirms sustainability commitment on World Tuna Day
48 minutes -
Mahama commissions Odumase Krobo Divisional Police HQ, boosts operations with vehicles
1 hour -
Roads Minister urges contractors to stay on site, assures prioritised payments
1 hour -
Suhuyini credits Ameri plant for averting 2024 power crisis in Kumasi
2 hours -
Thirteen killed in Israeli strikes on southern Lebanon, health ministry says
2 hours -
Tano North MP sounds alarm over galamsey devastation, accuses officials of shielding perpetrators
2 hours -
Digital wealth, analog poverty: Why technology isn’t closing the gap
2 hours -
World Relays: Ghana miss automatic qualification after finishing 4th in heat
2 hours -
NACOC disrupts suspected drug network in Winneba ahead of Aboakyiri Festival
2 hours