Documents filed on behalf of the Attorney General alleges that Consultancy Services under the Saglemi Housing project were awarded three times, costing the taxpayer an estimated $13m.
First, in April 2013, the Architectural & Engineering Services Limited (AES Ltd), which had the consultancy contract, decided to subcontract its Services to Vito-Hugo-Coordenacaoe Gesto De Projectos (VHM) for a period of 24 months.
A maximum amount of $2.9m was to be paid VHM, while AESL was to take not more than $2m.
In April 2015, while VHM and AESL are said to have been providing the said Services, the Ministry of Works and Housing is alleged to have entered into another contract for consultancy services with Ridge Management Solutions DEC-LLL (RMS).
RMS was represented by its director and majority shareholder, Nouvi Tettey Angelo. This was to span a period of three months at a contract sum of $5.6m.
This was at a time RMS was not registered in Ghana as a company. However, the AG’s office says its investigations revealed Mr Angelo is also a Director of VHM awarded the same services two years earlier.
In August of 2016, then Minister of Works and Housing Kwaku Agyeman-Mensah is alleged to have entered into yet another consultancy agreement with RMS, this time christened “marketing implementation services” for a sum of $2.5m.
The AG notes that all this while, these Consultancy Services were being performed by AESL and VHM as per the agreement signed in 2013.
This the AG claims had been extended at various times by Mr Agyeman-Mensah and Ziblim Yakubu, former Chief Director at the Ministry.
The AG concludes that further payments were made to AESL, VHM and RMS far more than the $5m stated as consultancy fees under the original Housing project agreement.
These payments the AG claims were without any evidence of work done contrary to the contract's requirement.
Former Ministers of Works and Housing, Collins Dauda and Kwaku Agyeman-Mensah, former Chief Director Ziblim Yakubu and two others are facing 52 charges for various roles said to have caused the state to lose money it borrowed to construct 5,000 housing units. Only 668 units are said to have been completed, with the AG describing them as “not habitable”.
Latest Stories
-
Northern Ghana to experience another bout of dust pollution – Ghana Meteorological Agency warns
22 mins -
Kwaku Antwi-Boasiako: Is Anti-LGBT+ Bill more supreme than the 1992 Constitution?
30 mins -
Mahama promises to build university in six new regions
36 mins -
Mahama promises to enhance ‘Okada’ business with electric tricycles, maintains need for legalisation
45 mins -
Ghana’s land litigation concerns presents threat to solar energy projects
52 mins -
African Games 2023: Joseph Commey makes semis; Walid Omar, two others eliminated in boxing event
57 mins -
African Games: Ghana’s men’s doubles duo one win from medal zone
58 mins -
More tough times ahead for Ghana’s cedi; cedi is 3rd worst currency in Africa – Bloomberg
1 hour -
IMF Boss urges Ghana to foster inclusive society amid anti-LGBTQ+ legislation
1 hour -
Recent depreciation of cedi not worrying; trend to reverse soon – Prof Turkson
1 hour -
We won’t allow aliens to elect our MP for us anymore – Effutu NDC PC James Kofi Annan
1 hour -
It is not a crime to show foreign movies during prime time – Lawyer
1 hour -
The era of omnichannel retailing and the faith of conservative brands
1 hour -
Extend mentoring to less privileged areas – Women in Engineering urged
2 hours -
Admaius Capital partners with Egyptian medicated-cosmetics business Parkville
2 hours