Documents filed on behalf of the Attorney General alleges that Consultancy Services under the Saglemi Housing project were awarded three times, costing the taxpayer an estimated $13m.
First, in April 2013, the Architectural & Engineering Services Limited (AES Ltd), which had the consultancy contract, decided to subcontract its Services to Vito-Hugo-Coordenacaoe Gesto De Projectos (VHM) for a period of 24 months.
A maximum amount of $2.9m was to be paid VHM, while AESL was to take not more than $2m.
In April 2015, while VHM and AESL are said to have been providing the said Services, the Ministry of Works and Housing is alleged to have entered into another contract for consultancy services with Ridge Management Solutions DEC-LLL (RMS).
RMS was represented by its director and majority shareholder, Nouvi Tettey Angelo. This was to span a period of three months at a contract sum of $5.6m.
This was at a time RMS was not registered in Ghana as a company. However, the AG’s office says its investigations revealed Mr Angelo is also a Director of VHM awarded the same services two years earlier.
In August of 2016, then Minister of Works and Housing Kwaku Agyeman-Mensah is alleged to have entered into yet another consultancy agreement with RMS, this time christened “marketing implementation services” for a sum of $2.5m.
The AG notes that all this while, these Consultancy Services were being performed by AESL and VHM as per the agreement signed in 2013.
This the AG claims had been extended at various times by Mr Agyeman-Mensah and Ziblim Yakubu, former Chief Director at the Ministry.
The AG concludes that further payments were made to AESL, VHM and RMS far more than the $5m stated as consultancy fees under the original Housing project agreement.
These payments the AG claims were without any evidence of work done contrary to the contract's requirement.
Former Ministers of Works and Housing, Collins Dauda and Kwaku Agyeman-Mensah, former Chief Director Ziblim Yakubu and two others are facing 52 charges for various roles said to have caused the state to lose money it borrowed to construct 5,000 housing units. Only 668 units are said to have been completed, with the AG describing them as “not habitable”.
Latest Stories
-
World Vision Ghana brings joy to Wa West children with mass birthday celebration
15 minutes -
NAIMOS arrest one foreign national and 7 Ghanaians in anti-galamsey operation in Ashanti Region
16 minutes -
Health Ministry announces mop-up exercise for validation and posting of health professionals
16 minutes -
GoldBod wins community backing for responsible mining support program in Ashanti Region
16 minutes -
Xenophobic attack: Why announce evacuation without preparation? – Minority caucus questions gov’t
20 minutes -
Government failed Ghanaians in South Africa — Minority slams evacuation delay
33 minutes -
Heavy downpour leaves Kaneshie, other parts of Accra flooded
36 minutes -
Mahama’s STEM push aims to build curious, creative students – Haruna Iddrisu
50 minutes -
Swimming stakeholders call for legitimate governance and constitutional elections in Ghana Swimming
1 hour -
Akatsi Police seize suspected cannabis consignment, driver escapes
1 hour -
EU investment in Ghana reaches $16bn – GIPC’s Boss
2 hours -
GPSCP II and TCDA partner to boost regulation and investment in tree crops sector
2 hours -
Ghana, Ethiopia business ties ripe for expansion – GIPC
2 hours -
Ghana-Russia Center signs landmark cooperation agreements at KazanForum 2026
2 hours -
Sankofa Gold Mine, Guangzhou Hozdo partnership signals revival push as Ghana’s Western mining sector heats up
2 hours