The Energy Ministry has dispelled claims that the country will be returning to the days when power supply had to be rationed due to inadequate energy generation capacity.
The Ministry in a rejoinder noted that its attention has been drawn to comments by former Minister of Power during the Mahama-led administration, Dr. Kwabena Donkor, suggesting the return of “dumsor”.
Dr. Kwabena Donkor is reported to have said that “dumsor” is imminent due to the “insignificant addition to our generation capacity.”
According to the Ministry, the claims made by the former Minister lack merit.
The Energy Ministry explained that "dumsor" was as a result of “poor hydrology due to over drafting of hydro dams, inadequate fuel supply to thermal plants, and financial challenges.”
The Communications and Public Affairs Unit of the Energy Ministry has assured that the country is currently not facing challenges with power generation.
The Ministry has revealed that there is the prudent management of hydro resources which include the hybridization of hydro dams due to “the 250MW Bul Solar project of which 50MW has been commissioned and operationalized, with the next phases on-going, is to curb the challenge of over drafting of the Bui Dam.”
“Secondly, under this government, gas flow is no longer uni-directional. The Takoradi Tema Interconnection Project (TTIP) is ensuring the reverse flow of indigenous natural gas from the West to the East to power our turbines.
"What this means is that we no longer have the phenomenon of stranded gas in the west of the country. Again, the Tema LNG project when completed soon, will allow the importation of LNG to support generation,” the Ministry added.
In view of the capacity generated by government, the Ministry is confident that, “there is no way that this country will go back to the dark days of 'dumsor'.”
Meanwhile, the Energy Ministry has urged Dr. Kwabena Donkor to first seek the correct information from the Ministry in future before going public.
The incorrect pronouncements made by the former Minister, the Ministry said has the tendency to mislead the public and cause unnecessary concerns.
“This is particularly due to the fact that he is a former Minister for Power and his pronouncements therefore carry some weight,” it added.
On the other hand, ongoing projects being undertaken by government, according to the Energy Ministry include:
a. Early Power: This is a 400MW power plant located at Tema which will be constructed in two phases made up of 200MW each. Phase 1A of the first phase (147MW) commenced commissioning in 2021 and completing commercial operation issues. The second part 18 of 53MW is also expected to come online this year. The final phase making up 400MW is expected to be commissioned by 2024.
b. Pwalugu Hydro and Solar Hybrid Plant: This is a 60MW hydroelectric plant in hybrid operation with a 50MWp Solar PV plant which is expected to be completed and commissioned by 2025. The plant will be located in the Upper East Region.
Latest Stories
-
Ghana committed to reshaping a better future for Africa—Foreign Minister
4 seconds -
New Ghana Statistical Service report exposes sharp district inequalities in health, hygiene and child welfare
1 minute -
ORAL investigations are proceeding well – Attorney General
5 minutes -
2025 Supercar Spectacle thrills fans with speed and star power
12 minutes -
2025 WASSCE: Chief Examiners’ report reveals many candidates failed to answer application-based questions
13 minutes -
FoSCel presents citation to NHIA for strengthening support for Sickle Cell treatment under NHIS
17 minutes -
Abuakwa South MP celebrates teachers in his constituency at inaugural awards ceremony
19 minutes -
Ato Forson reported to CHRAJ over discriminatory ex-gratia payments
19 minutes -
Shatta Wale pushes me to sing more on my songs – Sarkodie
27 minutes -
The Wire actor James Ransone dies aged 46
27 minutes -
OSP exists largely on paper – Majority Chief Whip Rockson Dafeamekpor
27 minutes -
This is how Wontumi Farms planned to spend GH¢18.7m Exim Bank loan
42 minutes -
AG vs Wontumi Farms: Full investigation outlined by the Attorney-General
47 minutes -
Major incident declared over canal ‘sinkhole’
51 minutes -
Obrafour collaboration gave me my industry stamp – Sarkodie
53 minutes