Senior Project Manager, Ing. Abdulai Mahama has explained the delay in the completion of the Ofankor-Nsawam road.
The project, which began in September 2022, was expected to be completed within 24 months but is currently about 60 per cent complete.
Speaking on Adom TV’s current affairs show, 'The Big Agenda' with Abena Opokua Ahwenee, Mr Mahama explained that the challenges causing the delay are beyond their control.
Among other things, he revealed that they had to demolish a shrine along the way, but were told the gods had travelled.
He said there were also issues to be addressed between settlers and landlords, the need to reposition ECG and GRIDCO high-tension wires among others.
“My sister, during construction, we encountered a shrine. We consulted the locals and were told the gods had travelled, which delayed us for three and a half months. We had to pay for two cattle and provide money before we were allowed to continue work,” Mr Mahama explained.
Regarding the project’s timeline, Mr Mahama said the road has a 20-year design duration, whereas all drainage systems are designed to last 50 years.
Latest Stories
-
Trump says Canada wants ‘benefits’ of being US state after trade talks collapse
16 minutes -
TikTok to pay $400m to US in one of largest child privacy settlements
25 minutes -
Asante Kotoko management doesn’t involve me in supporters mobilization – McBrown
28 minutes -
Frustration builds in Indiana town struggling without power for 12 days
36 minutes -
‘Jesus was accused; he kept quiet’ – Afenyo-Markin softens stance on legal action against Gyamfi
48 minutes -
NSMQ 2026: Accra High steals one-eighth ticket from Sunyani SHS in stunning final-round twist
49 minutes -
Kejelcha breaks men’s half marathon world record by 29 seconds
49 minutes -
Nkoko Nkitinkiti programme has failed – Afenyo-Markin claims
1 hour -
NDC yet to deliver key 2024 campaign promises – Afenyo-Markin
1 hour -
Adamus welcomes 12-month roadmap to revive mine, restore investor confidence
2 hours -
T-bills: Government records 162% oversubscription, interest rates slump
2 hours -
UPSA moves to turn student research into market-ready solutions
2 hours -
Presby SHS, Suhum honour late coordinator with dominant One-Eighth qualification
3 hours -
NDC Volta team tracks development projects across four districts
3 hours -
NSMQ 2026: St. Monica’s SHS snatch one-eighth ticket from Amenfiman SHS in dramatic showdown
3 hours