The Pwalugu dam which is said to be the largest investment yet in the Northern Region of Ghana since independence at the cost of close to a billion dollars has been halted due to rains and floods.
The Vice President of Ghana, Dr Bawumia reiterated his stance on the popular multipurpose Pwalugu dam project as one that would control and permanently end the Bagre dam spillage, but upon his visit to the site, it was noticed that the rains are hindering the progress of the construction.
"The contractors were waiting to do the earthworks, I went there recently and realised for myself that the rains are hindering progress, the rains must end first, the floods are still there," he said.
"Contractors are on-site with the needed machinery, but they want the water to dry up so they begin the earthworks. The clearing and camping have begun, they are ready to move with the work but the rains have to stop first,“ he said.
In a one-on-one interview on Asempa FM, the Vice President mentioned that the Pwalugu Dam after its completion would "irrigate another 12,000 plus hectares, control floods we face every year and generate electricity."
The Vice President while on tour in the region also donated some relief items including soap, rice, blankets, mattresses, water, cups, basins, used clothes, mats and oil among others as well as cash amount of ¢10,000.00 to the affected victims.
Dr Bawumia as part of his working visit to the region further inspected works on the reconstruction of the Tono Dam spillway channel in the Kassena-Nankana Municipal which got broken in October, 2019 after several days of heavy torrential rainfall.
Latest Stories
-
NHIA accelerates claims payments, advances talks on new tariffs
6 minutes -
CHAG facilities remain backbone of NHIS in rural Ghana – NHIA boss
10 minutes -
Accra floods disrupt business activities as traders, trucks are stranded on major roads
20 minutes -
GRIDCo, ECG temporarily shut down Mallam and Achimota substations over flood risk
31 minutes -
Floodwaters cut off Winneba–Cape Coast highway, leaving hundreds stranded
32 minutes -
UTAG-UCC rejects GTEC promotion harmonisation plan, cites threats to university autonomy
48 minutes -
GNFS battles major rubber factory fire at Circle as heavy rains hamper response
1 hour -
GAF deploy troops to flood-hit communities in Accra under ‘Operation Boafo’
2 hours -
Ghana School of Law reschedules ADR and Ghana Legal System exams to June 30 after Accra flooding
2 hours -
Adopt NPA’s transparent pricing model to build public trust – CEMSE tells PURC
2 hours -
Work from home as flooding intensifies – Interior Minister urges Accra residents
2 hours -
US Embassy hosts Black Stars watch party in Tamale to strengthen community engagement
2 hours -
Kwame Nkrumah Circle floods leave hundreds of commuters stranded
2 hours -
NADMO announces toll-free line for flood and disaster emergencies
2 hours -
Flooding disrupts movement on Accra–Kumasi highway
2 hours