Tullow Ghana Limited, on behalf of the Jubilee Joint Venture Partners, says it has completed of the Interim Spread Mooring of the Jubilee FPSO, Kwame Nkrumah.
This involves the installation of an interim anchoring system on the stern of the FPSO to hold the vessel in place, completes the first phase in the Turret Remediation Project which will eventually provide the FPSO with a long term mooring solution.
In addition to the existing anchor lines on the FPSO’s turret, the FPSO is now firmly secured in position by six anchor lines, three on each side of the stern of the vessel allowing the three tug boats which have been keeping the FPSO in place over the last 11 months to return to shore.
This phase of the project has been achieved with production maintained at optimal levels with the exception of short, planned reductions for technical reasons. Oil and gas offtakes have also continued in the new normal state of operations.
The JV partners are now analysing options for the next phase of the project which will involve modifications to the turret systems for long-term operations.
Detailed planning for these works continues with the JV Partners and the Government of Ghana, with final decisions and approvals being sought in the first half of 2017 and work expected to be carried out in the second half of 2017.
Managing Director of Tullow Ghana Ltd commented today, Charles Darku said, “it is a highly complex and significant achievement for an FPSO to be held to one heading by tugs within a few degrees for 12 months and for production to have been maintained throughout.
"We would like to recognise the strong collaboration with our Joint Venture Partners, the Government of Ghana and our key contractors in achieving this important milestone,” he said.
Latest Stories
-
UTAG demands removal of GTEC leadership, issue 14-day deadline
2 minutes -
Police take steps to prevent future highway attacks after fatal robbery attack
5 minutes -
Free Primary Healthcare won’t cover referrals to higher facilities — Health Minister
23 minutes -
Free primary healthcare to prevent emergencies and reduce ‘No Bed Syndrome’- Health Minister
24 minutes -
Free Primary Healthcare to be launched on Wednesday — Health Minister
29 minutes -
No charges for free primary healthcare, only valid ID required – Akandoh
31 minutes -
Only 2% of public health facilities fully equipped among 60% surveyed — Akandoh reveals
35 minutes -
Delay in Petroleum Hub project affecting youth expectations – Paramount Chief warns
41 minutes -
Nigeria Air Force orders investigation after dozens killed in airstrike
43 minutes -
Free Primary Healthcare a “national reset”—Health Minister urges early care
44 minutes -
Improved sanitation, security making Kasoa business-friendly – MP
47 minutes -
Free Primary Healthcare to be rolled out in phases, with 150 districts in phase one – Health Minister
52 minutes -
Free Primary healthcare to cover basic services at no cost – Health Minister
53 minutes -
Four foreigners, three Ghanaians arrested in illegal mining raid along Boin River
58 minutes -
Gov’t procures 24,534 medical equipment ahead of free healthcare rollout
1 hour