Construction work on sections of the Tema-Aflao highway has resumed after a break of approximately 15 months, following an appeal by the Minister for Roads and Highways, Kwame Governs Agbodza, for contractors to return to the site.
BHM International Construction, the contractor responsible for the 17-kilometre stretch, returned to the site on Monday, 7th April 2025, to continue work on the project, which runs from the Tema Roundabout to the Central University campus at Miotso.
The project had been suspended in December 2022 due to funding constraints.
Speaking on behalf of the company, Client Relations Manager, Wisdom Adonu, called on the government to reinstate the $105 million loan facility required to complete the project within the revised 18-month timeline.
"This is our commitment to the project. We have returned to the site, and we appeal to the government to do its part by restoring the loan facility," he said.
The ongoing work begins one kilometre east of the Tema Expressway Roundabout, passing through areas such as Dawhenya, and terminates about three kilometres east of the Central University intersection.
Latest Stories
-
NPP-USA faces internal dispute over disqualification of 5 aspirants ahead of branch elections
7 minutes -
Greater Accra records 1,054 vehicle interceptions in police crackdown on illegal sirens
8 minutes -
80 CSOs urge government to release full Constitutional Review Committee report
16 minutes -
US Judge says OSP failed to provide evidence linking Ofori-Atta to criminal wrongdoing
32 minutes -
Today’s Front Pages: Tuesday, July 21, 2026
55 minutes -
Lands and Mines Watch welcomes Wontumi verdict, urges tougher action against illegal mining
1 hour -
West African women leaders declare violence against women a legislative emergency, demand urgent action
1 hour -
Cedi slides again as dollar demand outpaces supply, depreciation hits 8.89%
2 hours -
Cedi weakens modestly in interbank market but remans stable in retail market; one dollar equals GH¢12.20
2 hours -
Inflation to return to medium-term target of 8 ± 2% – BoG
2 hours -
‘Cock-and-bull story’ – Kpebu says Wontumi’s reclamation defence fell apart
2 hours -
GEPA, Netherlands CBI sign MoU to formalise trade partnership
2 hours -
Banks write-off GH¢883.7 million as bad debt in 4-months of 2026
2 hours -
NPP gov’t had already disowned Wontumi over alleged illegality before power changed – Dafeamekpor
3 hours -
High Court erred in law in Wontumi judgment – John Darko
3 hours