The Auditor-General has cited Makro Structures Limited for abandoning a Covid-19 isolation and treatment centre project in Nalerigu of the North East Region.
According to the Audit Service, the contractor was awarded the ¢15 million project by government on May 11, 2020, and was charged to complete it in October 2022.
It was subsequently paid GH¢4.5 million which constitutes 30 per cent of the full amount to commence the designing, construction and equipping of the centre.
However, the Auditor-General in its latest report into government’s Covid-19 expenditure between March 2020 and June 2022, indicated that Makro Structures Limited upon starting works in October 2021 undertook civil works up to 10 per cent and abandoned the site in December 2021.
“Written communication from the Director of the Infrastructure Directorate, reveals that the Director had made several efforts to get the contractor to the site, but the contractor was unwilling to continue.
“The absence of a performance bond has contributed to the difficulty in recovering the amount paid to the contractor for non-performance,” parts of the audit report read.
The Auditor-General, Johnson Akuamoah Asiedu, further noted that the abandonment impeded government’s effort to provide a treatment and holding centre in the North East Region.
He, however, recommended that the Chief Director should recover the mobilisation amount, terminate the contract and re-award the construction of the project to a more committed contractor.
Latest Stories
-
It’s my first Christmas as your come-back President, I am grateful for your trust – Mahama
9 minutes -
Myth or Reality? A Musical Epic of the Economic Magic of Burkina Faso
12 minutes -
December in Ghana is alive – Creatives say the issue is amplification, not activity
28 minutes -
Jubilee Park comes alive as thousands gather for Sonnie Badu’s ‘Rhythms of Africa’ concert
40 minutes -
NDC not considering third-term bid for Mahama – Suhuyini
42 minutes -
4-year presidential term has limited Ghana’s development – Alhassan Suhuyini backs 5-year proposal
47 minutes -
Mahama’ rising popularity is giving NPP sleepless nights – Suhuyini
52 minutes -
STC, Metro Mass buses to feature smart monitoring and cashless systems in 2026 – Transport Minister
58 minutes -
Suhuyini: Electioneering period reforms possible, but campaigning can’t be legislated
1 hour -
Lack of regulation fuelled motorcycle accidents – Transport Minister
1 hour -
NSA scandal: AG hints at plans to file civil suit against suspects
1 hour -
Trade and industry set for stronger growth in 2026 – Ofosu-Adjare
1 hour -
UG commissions innovation enclave to drive youth entrepreneurship
2 hours -
Black Sheep Foundation honours 255 teachers in maiden Christmas initiative
2 hours -
Screams for help and panic as tourists rescued from fatal Laos ferry disaster
2 hours