The Kumasi International Airport is set for operations in August this year, two months ahead of its scheduled completion date.
Currently, some equipment have been installed with simulation exercise completed.
The scope of work on the Airport includes the extension of existing runway pavement from 1,981 metres to 2,320 metres.

The construction of a new taxi link and apron, as well as two new apron parking stands, is among other essential facilities.
The terminal will have the capacity to handle 800,000 passengers per annum.
Presently, the terminal building is near completion with most installations done, while works on the control tower are in an advanced stage.
Ashanti Regional Minister, Simon Osei Mensah, during an inspection at the facility, expressed satisfaction at work done so far.
“Of the greatest importance to me is that they have the best scanner which can allow flight from here to move to even the United States which has the most difficult eligibility criteria in terms of aviation; they say the scanner we have qualifies for the requirement of the US Airlines,” he said.

He added: “If you look at the departure and arrival hall, it’s almost completed. All the facilities have been installed but you will need the fire service area, the control tower and others, which once completed, will have a simulation exercise.”
Once works on the project are completed, the existing terminal which has outlived its usefulness is expected to be demolished.

As part of government’s vision to expand economic activities in the city, efforts are being made to improve infrastructure.
Already, a 100km town road project within the Greater Kumasi enclave has been completed by Contracta Construction.

Mr. Osei Mensah says the government is committed to developing majority of roads in Kumasi by the end of its tenure.
“People say they don’t see the roads, it’s because some of the roads are localised. If you are not living here at Kentinkrono, how do you know this road is constructed?

"As you can witness, excluding other contracts within the Greater Kumasi enclave, we are expecting 400km of road constructed. By the time it is done we would have covered many areas in Kumasi,” he emphasised.
Latest Stories
-
World Relays 2026: Ibrahim Fuseini details how he missed flight to Botswana
10 minutes -
Kobby Kyei heads to Nairobi for Africa Forward Summit 2026
11 minutes -
What to know about hantavirus, suspected virus outbreak on Atlantic cruise ship
13 minutes -
Education Minister directs GES to reserve recruitment quota for persons with disabilities
16 minutes -
International Schools Tennis tournament uncovers young talent in Accra
19 minutes -
Mahama rallies chiefs, security agencies against rising drug abuse among youth
22 minutes -
Lifeline for Afife R/C Primary School as JOBerg supports GETFund with GH¢2.25m for classroom and toilet project
23 minutes -
Josh Blakk drops live EP as he eyes Best Male Vocal honour at TGMA
23 minutes -
Beyond the headlines: Rethinking emergency care in Ghana
26 minutes -
Ghana facing moral decline in leadership across institutions – Prof Karikari
28 minutes -
Play House: DJ Mensah launches state-of-the-art recording studio in Accra
36 minutes -
Education Minister calls on WAEC to review its mode of transporting examination materials
39 minutes -
Asantehene honours Angela List
47 minutes -
Fate of OSP, future of anti-corruption mandate
49 minutes -
Auto Bridge Ghana enters market to simplify vehicle importation and sales
1 hour