Minister of Education, Dr Yaw Osei Adutwum, has disclosed that work on the first phase of Ghana’s first-ever Creative Arts Senior High School (SHS), being constructed at Kwadaso in the Ashanti Region, will be completed in December 2021.
Currently, about 60% of the project has been executed by the two main contractors, Messrs Golden Mainland and Uton Engineering, he hinted.
Facilities being worked on included an administration block, a 750-capacity girls’ dormitory, a 500-capacity boys’ dormitory, classroom blocks, and a studio laboratory.

“The government is committed to diversifying the economy by grooming young talents for the creative arts industry to enhance job creation and poverty alleviation,” Dr Adutwum told the Ghana News Agency (GNA) at Kwadaso after he inspected the progress of work on the project.
He was accompanied by Dr Kingsley Nyarko, Kwadaso MP, and Mr Agyenim Boateng, the Municipal Chief Executive (MCE).
Work on the project commenced in 2019, and on completion, would spearhead the nation’s bid to identify and harness young talents in areas encompassing literature, music, drama, visual arts, film, dance, sound engineering and film production.
Dr Adutwum said a team of experts had been put together to develop the curriculum for the institution, adding that the operationalization of the nation’s premier Creative Arts SHS is expected to commence soon.

“The vision of the government is very clear, that in promoting science, technology, engineering and mathematics, we do not have to leave out the creative arts,” he observed.
The Creative Arts industry, according to the Minister, has many prospects for the younger generation.
Therefore, the government was committed to investing in the sector to brighten the future of the youth.

Kwadaso MP, Dr Kingsley Nyarko, said the authorities had been monitoring the project to ensure its successful completion.
Mr Daniel Ohene, the Project Coordinator for Messrs Golden Mainland, who guided the delegation for the project inspection, assured of the contractors’ resolve to complete the work as scheduled.
Latest Stories
-
Cagliari eye loan swoop for Ibrahim Sulemana amid Parma and Sassuolo interest
2 minutes -
Morocco beat Nigeria on penalties to set up AFCON final against Senegal
3 hours -
NaCCA Director-General apologises as withdrawn teacher manual sparks national outrage
3 hours -
Mane destroys Salah’s Afcon dream again – will he get another chance?
4 hours -
‘If Flick hadn’t come, I would have left Barca’ – Raphinha
4 hours -
Real Madrid stunned by second division Albacete in Copa del Rey
4 hours -
Tottenham sign Gallagher from Atletico for £35m
4 hours -
Amateur stuns world’s best Jannik Sinner to win A$1m in Melbourne
4 hours -
FBI searches home of Washington Post reporter in classified documents probe
5 hours -
Trump administration pauses immigrant visa processing for 75 countries
5 hours -
UK–Ghana crack down on immigration crime as fugitive smuggler jailed
5 hours -
Ghana’s Benjamin Arhin shines on Internacional debut with Man of the Match display
5 hours -
Stanbic Bank Ghana maintain top rank in Customer Experience Leadership in 2025 KPMG Assessment
6 hours -
Newmont-backed AI smart lab powers Kona D/A students to victory at Ghana Robotics Competition
6 hours -
Venezuelan acting president says hundreds of prisoners have been released since December
6 hours