Minister of Education, Dr Yaw Osei Adutwum, has disclosed that work on the first phase of Ghana’s first-ever Creative Arts Senior High School (SHS), being constructed at Kwadaso in the Ashanti Region, will be completed in December 2021.
Currently, about 60% of the project has been executed by the two main contractors, Messrs Golden Mainland and Uton Engineering, he hinted.
Facilities being worked on included an administration block, a 750-capacity girls’ dormitory, a 500-capacity boys’ dormitory, classroom blocks, and a studio laboratory.

“The government is committed to diversifying the economy by grooming young talents for the creative arts industry to enhance job creation and poverty alleviation,” Dr Adutwum told the Ghana News Agency (GNA) at Kwadaso after he inspected the progress of work on the project.
He was accompanied by Dr Kingsley Nyarko, Kwadaso MP, and Mr Agyenim Boateng, the Municipal Chief Executive (MCE).
Work on the project commenced in 2019, and on completion, would spearhead the nation’s bid to identify and harness young talents in areas encompassing literature, music, drama, visual arts, film, dance, sound engineering and film production.
Dr Adutwum said a team of experts had been put together to develop the curriculum for the institution, adding that the operationalization of the nation’s premier Creative Arts SHS is expected to commence soon.

“The vision of the government is very clear, that in promoting science, technology, engineering and mathematics, we do not have to leave out the creative arts,” he observed.
The Creative Arts industry, according to the Minister, has many prospects for the younger generation.
Therefore, the government was committed to investing in the sector to brighten the future of the youth.

Kwadaso MP, Dr Kingsley Nyarko, said the authorities had been monitoring the project to ensure its successful completion.
Mr Daniel Ohene, the Project Coordinator for Messrs Golden Mainland, who guided the delegation for the project inspection, assured of the contractors’ resolve to complete the work as scheduled.
Latest Stories
-
Akosua Manu refutes Kennedy Agyapong; Bawumia campaigned for NPP in Adenta
10 minutes -
Government’s reset agenda will take time to materialise – Ho Central MP
11 minutes -
Police seize over 1,600 parcels of suspected narcotic drugs in major bust
13 minutes -
Miguel Ribeiro Fiifi Brandful
14 minutes -
Trade Minister storms Abossey Okai to enforce fair pricing ,curb middlemen exploitation
19 minutes -
Hopeson Adorye calls for firm action against GWCL over persistent water shortages
28 minutes -
Two burnt to death in fiery Offinso road accident
49 minutes -
NPP flatly rejects Frimpong-Boateng’s claims, defends 2024 flagbearer vote
1 hour -
NPP initiates process to expel Prof Frimpong-Boateng over “fake party” comments
1 hour -
Family of late Sawla-Tuna-Kalba MP appeals to President Mahama over GH¢944,955 demand blocking his burial
2 hours -
Today’s Front pages: Tuesday, January 13, 2026
2 hours -
Galamsey fight: Western Regional Minister calls for real-time monitoring of water bodies
2 hours -
NPP has lost its identity, the current party is “fake” – Prof Frimpong-Boateng
3 hours -
GRA targets GH¢225bn revenue in 2026 as VAT reforms take effect
3 hours -
Heath Goldfields promises community-centered revival of Bogoso-Prestea Mine
3 hours