Works and Housing Minister Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024, with project coordinators and contractors to address delays plaguing the critical initiative.
"We've assessed how far the project is going and we've had several site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.
![](https://www.myjoyonline.com/wp-content/uploads/2024/04/image-428-1024x683.png)
He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays.
Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval.
![](https://www.myjoyonline.com/wp-content/uploads/2024/04/image-431-1024x683.png)
Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.
![](https://www.myjoyonline.com/wp-content/uploads/2024/04/image-429-1024x731.png)
Addressing the Hurdles
The Minister outlined a series of measures to tackle these challenges. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up critical work areas.
![](https://www.myjoyonline.com/wp-content/uploads/2024/04/image-432-1024x731.png)
On the financial front, Mr Oppong Nkrumah reassured contractors that government is actively working with Parliament to make available the outstanding funds, including the diverted $65 million.
A Race Against Time
![](https://www.myjoyonline.com/wp-content/uploads/2024/04/image-430-1024x683.png)
While acknowledging the challenges, Mr Oppong Nkrumah emphasized the urgency of the completion of the GARID projects.
He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.
Latest Stories
-
Paris 2024: Opening ceremony showcases grandiose celebration of French culture and diversity
2 hours -
How decline of Indian vultures led to 500,000 human deaths
3 hours -
Paris 2024: Ghana rocks ‘fabulous fugu’ at olympics opening ceremony
3 hours -
Trust Hospital faces financial strain with rising debt levels – Auditor-General’s report
4 hours -
Electrochem lease: Allocate portions of land to Songor people – Resident demand
4 hours -
82 widows receive financial aid from Chayil Foundation
4 hours -
The silent struggles: Female journalists grapple with Ghana’s high cost of living
4 hours -
BoG yet to make any payment to Service Ghana Auto Group
4 hours -
‘Crushed Young’: The Multimedia Group, JL Properties surprise accident victim’s family with fully-furnished apartment
5 hours -
Asante Kotoko needs structure that would outlive any administration – Opoku Nti
5 hours -
JoyNews exposé on Customs officials demanding bribes airs on July 29
6 hours -
JoyNews Impact Maker Awardee ships first consignment of honey from Kwahu Afram Plains
7 hours -
Joint committee under fire over report on salt mining lease granted Electrochem
7 hours -
Life Lounge with Edem Knight-Tay: Don’t be beaten the third time
7 hours -
Pro-NPP group launched to help ‘Break the 8’
8 hours