Audio By Carbonatix
Works and Housing Minister Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024, with project coordinators and contractors to address delays plaguing the critical initiative.
"We've assessed how far the project is going and we've had several site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.

He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays.
Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval.

Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.

Addressing the Hurdles
The Minister outlined a series of measures to tackle these challenges. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up critical work areas.

On the financial front, Mr Oppong Nkrumah reassured contractors that government is actively working with Parliament to make available the outstanding funds, including the diverted $65 million.
A Race Against Time

While acknowledging the challenges, Mr Oppong Nkrumah emphasized the urgency of the completion of the GARID projects.
He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.
Latest Stories
-
NDC parliamentary leadership reshuffle secured 2024 election victory – Asiedua Nketiah
26 minutes -
Agbodza visits Adaklu-Helekpe mudslide victims, warns of more danger around mountain
31 minutes -
TTAG urge government’s urgent action on recruitment and postings
43 minutes -
World Vision Ghana brings joy to Wa West children with mass birthday celebration
59 minutes -
NAIMOS arrest one foreign national and 7 Ghanaians in anti-galamsey operation in Ashanti Region
59 minutes -
Health Ministry announces mop-up exercise for validation and posting of health professionals
60 minutes -
GoldBod wins community backing for responsible mining support program in Ashanti Region
60 minutes -
Xenophobic attack: Why announce evacuation without preparation? – Minority caucus questions gov’t
1 hour -
Government failed Ghanaians in South Africa — Minority slams evacuation delay
1 hour -
Heavy downpour leaves Kaneshie, other parts of Accra flooded
1 hour -
Mahama’s STEM push aims to build curious, creative students – Haruna Iddrisu
2 hours -
Swimming stakeholders call for legitimate governance and constitutional elections in Ghana Swimming
2 hours -
Akatsi Police seize suspected cannabis consignment, driver escapes
2 hours -
EU investment in Ghana reaches $16bn – GIPC’s Boss
2 hours -
GPSCP II and TCDA partner to boost regulation and investment in tree crops sector
2 hours