Works and Housing Minister Kojo Oppong Nkrumah has tasked contractors working on the Greater Accra Resilient and Integrated Development (GARID) project to expedite construction works to mitigate the risk of flooding in the Capital during the rainy season.
The Minister’s directive came in a meeting on Friday, April 12, 2024, with project coordinators and contractors to address delays plaguing the critical initiative.
"We've assessed how far the project is going and we've had several site visits to see for ourselves the kind of work that's going on. After this appraisal, it's fair for us to say that the project is not moving as quickly as we all expected," he said.

He highlighted various bottlenecks hampering the project. The initial project framework, the Minister explained, mandated a two-step review process for every task, creating unnecessary delays.
Additionally, compensating project-affected residents to facilitate work in certain locations encountered setbacks.
Further, the Minister pointed out instances where contractors deviated from project specifications without seeking prior approval.

Perhaps the most concerning delay stemmed from a budgetary reallocation with a significant portion of project funds, estimated at $65 million, diverted towards COVID-19-related expenditures.

Addressing the Hurdles
The Minister outlined a series of measures to tackle these challenges. To address the compensation delays, he announced that provisions have been made to ensure swift payments to affected residents, freeing up critical work areas.

On the financial front, Mr Oppong Nkrumah reassured contractors that government is actively working with Parliament to make available the outstanding funds, including the diverted $65 million.
A Race Against Time

While acknowledging the challenges, Mr Oppong Nkrumah emphasized the urgency of the completion of the GARID projects.
He said the impending rainy season poses a serious threat to flood-prone communities hence, contractors must act swiftly to safeguard lives and infrastructure.
He reassured contractors of the Ministry’s support in providing the needed support to ensure work progresses with speed.
Latest Stories
-
NAIMOS dawn operation leads to arrest of 49 suspected illegal miners after ambush on taskforce in Ahanta West
2 minutes -
Energy sector woes stem from political interference, not leadership failure — Kofi Bentil
21 minutes -
Communication around power outages has been ‘insincere’— Kofi Bentil
24 minutes -
President Mahama breaks ground for modern 24-hour market in Asesewa
2 hours -
Video: Daniel Kofi-Kyereh ranks Andre Ayew above Essien and Appiah in blind ranking game
2 hours -
Mensa Otabil launches new book, ‘Leading the Church’, emphasizes governance and leadership transition
3 hours -
Gov’t considers absorbing Western Rail Line reconstruction under Big Push Programme
5 hours -
Don’t store bread beyond four days – Baker advises consumers
6 hours -
Ghana-Korea trade hits $380 million amid growing cultural, investment ties
6 hours -
Why Ghana’s anti-corruption watchdogs are being dismantled — And the Supreme Court may seal their fate
7 hours -
Haruna Iddrisu vows to hike teacher recruitment numbers
8 hours -
First batch of 2026 Ghanaian pilgrims depart Tamale for Mecca
8 hours -
Police dismantle robbery gang in Upper East; 4 in custody, 2 dead during operation
9 hours -
Joseph Opoku’s late strike caps impressive run for Zulte Waregem
9 hours -
Multimedia Egg Market extended to today, Saturday, May 2
9 hours