Ghana has taken full ownership of the 250-megawatt (MW) power production plant from the African and Middle East Resources Investment Group, otherwise known as AMERI Energy.
The 10-unit barge, with capacity to generate 25MW each, totaling 250MW, which is commissioned on natural gas, is set to be moved to Anwomaso in Kumasi in the Ashanti Region.
The takeover and the relocation of the plant, the Ministry of Energy said, would rake in about $31 million annually from power export and $4 million as saving on transmission loss cut back.
The takeover
The power barges were handed over to the Volta River Authority (VRA), which received the plant, on behalf of the government, at the Aboadze Power Enclave in the Shama District in the Western Region yesterday.
It comes after the expiry of the five-year production and sale of power agreement signed between the government and the United Arab Emirates (UAE)-based company.
The Minister of Energy, Dr Matthew Opoku Prempeh, in a speech read on his behalf by one of his Deputy ministers, Mr William Owuraku Aidoo, said the deployment of the power plant to the Ashanti Region was strategic.
He said from a barge, the power plant would now be mounted on a trailer for it to be relocated to Anwomaso to improve the reliability of power supply in the middle and the northern sections of the power grid and for export.
Preparation
He said preparatory works at the site where the plant would be sited were at an advanced stage and on schedule for completion.
Dr Prempeh said the project would also promote the extension of the gas pipeline, which hitherto ended in the Western Region, saying: “The presence of natural gas in the region will stimulate other productive non-power uses of our indigenous natural gas resource.”
He said the government remained committed to a vision of a stable, robust, affordable power supply, as that was key to industrial growth.
“We promised to keep the lights on, and the ministry is doing exactly that, despite a few challenges. In achieving this, let me say that the Amandi Power Project — a 200MW Twin City Energy Project — has been completed, achieved commercial operation and dispatching power to the grid,” he said.
Bui solar
The minister indicated that a 50MW grid-connected solar plant at the Bui Hydro Generating Station had also been completed and commissioned.
“We have continued with improvement in the transmission system reliability by implementing other projects. These projects include the Kumasi-Kintampo Lot of the 330KV Kumasi-Bolgatanga Transmission Line Project which is complete and the line has been energised,” he said.
Dr Prempeh added that the Volta-Achimota Lot of the 161KV Volta-Achimota-Mallam Transmission Line Upgrade Project was 83 per cent complete, while the Achimota-Mallam segment was 55 per cent complete.
Others are the Pokuase Bulk Supply Point Project, which has been completed, and the Kasoa Bulk Supply Point Project, which comprises a re-construction of a section of the 161kV Winneba-Mallam Transmission lines and a tie-in-works, which is almost complete.
Interconnection transmission
The minister announced that the government was securing funding to improve the National Interconnection Transmission System (NITS) in the Ashanti and the Northern regions (Siemens–Ghana collaboration) and commence the construction of the GRIDCo Western Corridor Transmission Upgrade Project (WCTUP).
He said the government was also committed to achieving universal coverage of electricity by 2024, saying 162 communities were connected to the national grid in 2021, with 512 communities at various stages of completion.
Electricity access rate, he said, had moved from 85.17 per cent in 2020 to 86.63 per cent in 2021.
“In 2022, the ministry will work to complete many projects, with approximately 800 towns expected to be connected to the national grid under the SHEP-4, SHEP-5 and Turnkey projects,” he said.
Power system
The Director of Thermal Generation at the VRA, Mr Edward Obeng-Kenzo, said Ghana’s power system currently had low voltage around the Ashanti Region to the northern part of the country.
“This is mainly because all the power plants in the country are located in the southern, eastern or western part of the transmission network,” he said.
He indicated that the only plants in the middle of the transmission network were the 400MW Bui Hydro Power plant and the Bui Power Solar project.
“Therefore, the relocation of the 250MW AMERI Power plant to the Ashanti Region will enable the country to export an additional 50MW to neighbouring Burkina Faso,” he said.
The benefits
The export of power, Mr Obeng-Kenzo said, would fetch an additional income of $31 million annually and also reduce transmission system loss by 15MW, estimated at $4 million or about GH¢23 million annually.
The Western Regional Minister, Mr Kwabena Okyere Darko-Mensah, commended the government for paying the full cost of the plant, saying its relocation would go a long way to help improve Ghana’s power system.
The Country Manager of AMERI Energy, Mr Francis Kofi Kpolu, said his outfit was happy with the achievement through the new lease model and expressed the hope that it would have other projects through future collaborations.
Background
The government, on February 15, 2015, entered into an agreement with AMERI Energy to build, own, operate and transfer (BOOT) the power barge for five years, after which the country would assume full ownership of the plant.
The AMERI deal was signed as an emergency power agreement to fill Ghana’s power generation gap, which was then in deficit, necessitating nationwide power rationing, which commonly became known as ‘Dumsor’.
During the five-year production and sale of power to the VRA, per the agreement with AMERI, the government, through the VRA, made payments to AMERI for the power produced and supplied to the VRA, just like any other independent power producer.
LC of $51 million
Again, the government, per the agreement, was required to provide a standby letter of credit (LC) for $51 million, which LC has been raised.
Per the agreement with AMERI, the government, through the VRA, made payments to AMERI for power produced and supplied to the VRA.
Latest Stories
-
Muslim coalition sounds alarm over loopholes in new anti-LGBTQI+ bill
8 minutes -
Maritime development key to Africa’s economic transformation – GEXIM
27 minutes -
CSOs push for electoral reforms, propose new law on campaign financing
38 minutes -
Nigeria celebrates historic seven-medal haul in Bamako
38 minutes -
SIC Insurance posts GH¢84m profit as revenue rises, but audit flags subsidiary liabilities
41 minutes -
Afreximbank invites Rugby Africa President Herbert Mensah to address the 33rd Annual Meetings on a Panel Exploring Sport as a driver of African Industrialisation
46 minutes -
From the classroom to the home: How one day in Bulingin is changing healthy habits for good
49 minutes -
Abronye remanded into police custody over failure to surrender passport
55 minutes -
World Rugby and Canal+ Group unite to bring the next two Rugby World Cups to fans across Africa
57 minutes -
Accra Central Police fire outbreak leaves over 140 personnel and their families homeless
59 minutes -
Many Africans see justice system as unequal, costly, and slow, according to the Afrobarometer survey reveals
1 hour -
Speakers at African Conference urge President Mahama to assent to anti-LGBTQ bill into law
1 hour -
Trump hits back at ‘unpatriotic’ vote after House rebukes him over Iran
1 hour -
IGP tasked to secure immediate accommodation for officers affected by Tudu fire outbreak
1 hour -
Ebola threat: Gov’t to build health posts at all land borders
1 hour