The Minister for Works, Housing and Water Resources, Kenneth Gilbert Adjei, has attributed delays in the resettlement of communities displaced by the Akosombo Dam spillage to land ownership disputes, legal constraints and difficult terrain.
Speaking to journalists on Wednesday, January 28, during the Government Accountability Series, Mr Adjei acknowledged that although construction of replacement housing has commenced, progress varies significantly across affected areas.
He disclosed that the Ministry, working with 19 Metropolitan, Municipal and District Assemblies, has so far validated 2,225 housing units for reconstruction for flood victims across four regions.
According to the Minister, Phase One of the resettlement programme involves 1,010 housing units located within three Critical Impact Zones — North Tongu, Central Tongu and South Tongu — all in the Volta Region.
Mr Adjei explained that contractors have been mobilised at eight sites across the three districts, with construction activities at various stages.
He noted that communities such as Agbetikpo-Ganyakope and Battor Aveyime have recorded steady progress despite logistical constraints and challenges related to land acquisition, while work in other locations has stalled.
“Construction at Mepe and Nglorlekpoe has stalled due to unresolved land ownership issues, legal disputes and unfavourable terrain,” the Minister said.
He added that most of the housing projects remain at the substructure level, with the pace of work largely dependent on site accessibility and the performance of contractors engaged on the programme.
Latest Stories
-
Disagreement must follow lawful paths, not weaponised – Minority welcomes NDC’s response to SC Kpandai ruling
3 minutes -
Telecel reaffirms strategic partnership in New Year courtesy call on Asantehene
6 minutes -
Mrs Georgina Owusu-Achiaw aka Afia Badu
12 minutes -
US Federal Reserve holds interest rates despite White House pressure
15 minutes -
GUTA unhappy about local cargo insurance directive
23 minutes -
Kpandai: NDC respects Supreme Court decision, but disagrees with ruling – Tanko-Computer
25 minutes -
Kpandai: Parliament must not outrun law or create ‘manufactured vacancies’ – Minority warns
31 minutes -
MTN Ghana commits US$2 million to Government’s One Million Coders programme
33 minutes -
BoG policy rate reduction welcomed, economic stability still key – GVCA CEO
34 minutes -
Daylight heist: Armed gang raid Diaso gold shop, escape with gold worth ¢8 billion
35 minutes