
Audio By Carbonatix
The Minister for Health, Kwabena Mintah Akandoh, has attributed the delay in commissioning the Weija Paediatric Hospital to the contractor’s failure to complete outstanding works and formally hand over the facility to the Ministry of Health.
Speaking in Parliament on Tuesday, July 7, the Minister rejected claims that the government was intentionally delaying the opening of the hospital, insisting that the facility is not yet ready for operations because key contractual obligations remain unresolved.
Mr. Akandoh said the Ministry has already prepared the necessary human resources required to operate the hospital and is ready to commence service delivery immediately after the official handover of the facility.
“We have on standby the full complement of staff for the facility,” he told Parliament.
He disclosed that the Ministry has engaged the contractor on several occasions to address outstanding concerns and is expected to hold a final meeting with the contractor on Thursday, July 10, following a request by the contractor to attend the discussions personally.
“The contractor is not in the country at the moment. We have invited him and on the 10th was his request that he would be available personally for us to conclude on the matters,” he said.
The Health Minister explained that although some medical equipment has been installed at the facility, other equipment is yet to be installed, while access to some installed equipment remains unavailable because the contractor has not provided the required access codes.
“When we send the Ghana Health Service staff to the facility, there are equipment that have not been installed and there are others that have been installed but we don’t have complete access and the project has not been handed over to the Ministry,” he said.
Mr. Akandoh stressed that the Ministry is working with the contractor to resolve the remaining issues and complete the handover process, assuring that the government will immediately proceed with commissioning once the facility is officially transferred.
“If the project is handed over this morning, in the next 24 hours, we don’t even need to do any fanfare, we will commission the project because we have a full complement of staffing for that particular facility,” he said.
He maintained that reports suggesting the Weija Paediatric Hospital has been completed and is only awaiting commissioning are inaccurate, noting that the project must first satisfy all contractual requirements before it can be fully operationalised.
Latest Stories
-
Absa Bank empowers Persons with Disabilities through financial literacy programme
4 minutes -
Joyce Bawah Mogtari calls for collective responsibility to tackle flooding and waste management challenges
15 minutes -
Agbodza warns contractors against using weather as excuse for road project delays
31 minutes -
Ghana Reference Rate rises to 10.59% in July, signalling possible increase in lending rates
33 minutes -
Asiedu Nketia urges Africa to move beyond raw material exports through industrialisation
36 minutes -
Contractor delaying Weija Paediatric Hospital handover, not government – Health Minister
38 minutes -
Auditor-General has recovered nearly GH¢12bn in disallowed expenditure in 2024 – PAC Chair
40 minutes -
Roads Minister urges contractors to adopt on-site design reviews to avoid project delays
40 minutes -
Agbodza criticises highways officials over failure to report delayed road projects
41 minutes -
Government approves rehabilitation of Achimota School roads ahead of centenary celebrations
44 minutes -
‘It’s been tough’ – Opare Addo says gov’t needed 18 months to understand youth jobs crisis
45 minutes -
Energy Minister engages AGI on strengthening partnership to support industry
49 minutes -
Bawah Mogtari urges Ghanaians to turn flood crisis into opportunity for sustainable sanitation practices
51 minutes -
Three KMA officers injured as residents resist demolition exercise in Kumasi
53 minutes -
Youth Ministry found ‘fragmented’ gov’t programmes holding back jobs – George Opare Addo
54 minutes