A high-powered Ghanaian delegation will assemble at the dockside of Singapore's Jurong Shipyard on Saturday, May 1, to participate in the commissioning of the Floating Production Storage and Offloading (FPSO) Vessel of the Jubilee Project.
The delegation, which would witness one of the most anticipated milestones of the Jubilee Phase One Development Project include Government officials and Chief Executives of the partners of Jubilee Project.
The construction of the FPSO began in 2008 and involved the conversion of an existing VLCC tanker by MODEC, a leading international company in the FPSO industry that has been providing engineering, construction, installation and operation services for the last 25 years.
The FPSO will set sail for its base in the Jubilee Field, offshore the western coast of Ghana two weeks after it has been named.
Mr Sateesh K. Dev, President and Head of Global FPSO Execution of MODEC said: "The standard and quality of the FPSO is world class.
This is one of the fastest conversions of a vessel into an FPSO that we have undertaken.
"To achieve this we have leveraged on our existing field-proven designs and used high-end suppliers and fabricators to ensure quality and reliability of equipment and systems."
Mr Dev said as one of the world's leading FPSO general contractors, MODEC can assure the government and Ghanaians and the Jubilee partners that "FPSO is one of our best FPSO's built so far".
The naming of the FPSO is a significant milestone in the entire Jubilee Phase One development programme as it is a key indication that the Jubilee Partners remain on schedule to deliver First Oil in fourth quarter of this year.
It also reaffirms the commitment of the partners to the project, underlining their capacity to manage and produce the Jubilee Field.
During the period of construction of the FPSO, a number of delegations have visited Singapore to acquaint themselves with the progress of work.
The delegation includes personnel from the Ministry of Energy, Ghana National Petroleum Company and other Jubilee partners.
Six weeks ago, a high powered Ghanaian media delegation also visited the construction site at the Jurong Shipyard in Singapore to see the progress of work for themselves.
All the delegations that have visited the FPSO have been hugely impressed by the sheer scale of the vessel and the work required to undertake the massive project.
The FPSO uses the biggest turret ever constructed in the oil industry and can process 120,000 barrels of oil a day. It has a storage capacity of 1.6 million barrels.
With a width of 65 meters, and 330 meters in length, the FPSO is about the size of three standard football fields put together.
It has 17 modules weighing more then 12,500 tons installed on it. The modules include a water treatment plant, crude separation plant, chemical injection plant, gas process and injection plant, the turret, electricity generation plant, and 120-room accommodation.
Mr Dai Jones, President and General Manager of Tullow Ghana Limited, Operator of the Jubilee Field, said, "The pace of construction of the FPSO, its magnitude and complexity, and the state-of-the-art technology deployed, demonstrate that the Jubilee Phase One project will set new standards for oil production.
"Our investment in the project also demonstrates that we are in Ghana for the long haul - to help develop Ghana's oil potential," he said.
Tullow operates 34.7 per cent of the Jubilee Field and is partnered by GNPC (13.75 per cent), Anadarko Petroleum (23.49 per cent), Kosmos (23.49 per cent), Sabre Oil and Gas (2.81 per cent) and EO Group (1.75 per cent).
Source: GNA
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Tags:
DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.
Latest Stories
-
‘The law is the law’ – Mahama insists as Asake pleads on Cyborg’s behalf over firearm incident
46 seconds -
Police arrest 2 over illegal possession of 2,600 AK-47 ammunition in Ashanti Region
3 minutes -
Goldbod is rewriting Ghana’s gold story and restoring national value – Senyo Hosi asserts
12 minutes -
Goldbod: Loss or no loss? The price of everything and the value of nothing
17 minutes -
Government settles US$709m Eurobond obligations ahead of due date
18 minutes -
Low inflation and cheaper imports show Goldbod’s true economic value – Senyo Hosi
21 minutes -
VAT reforms: GRA raises registration threshold to GH¢750,000, cuts rate to 20% from Jan. 2026
22 minutes -
NPP Primaries: Dr Bawumia takes commanding 73% lead — latest Global InfoAnalytics report
34 minutes -
DGPP helped Ghana defy IMF currency forecasts and stabilise the Cedi – Senyo Hosi
35 minutes -
Guinea junta chief wins presidency in controversial election
38 minutes -
Cassava from reclaimed mine lands found to contain unsafe cyanide and lead levels – Study reveals
45 minutes -
Gov’t settles $709m eurobond payment ahead of schedule – Ato Forson
52 minutes -
Fuel prices set to drop from Jan 1, 2026 on cedi strength and falling crude prices
54 minutes -
‘Be vigilant, be professional’ – Private security guards urged to stay alert during festivities
58 minutes -
NPP race: Bawumia holds commanding lead – Global InfoAnalytics
1 hour