South Africa's Eskom has managed to restore eight units at power plants after implementing its highest stage of controlled power cuts early on Sunday, the power utility said after multiple failures at Majuba and Camden power stations over the weekend.
On Saturday, Eskom applied Stage 3 power cuts, known locally as load-shedding, effectively cutting 3,000 megawatts to the national grid.
"Of the 10 units that we lost overnight, we have essentially returned six units," Eskom group CEO Dan Marokane told reporters on Sunday.
He said five to six units were expected to become operational during the day, bolstering the 3,200 MW of capacity recovered overnight.
"We anticipate to get out of this stage by the end of the week," he said, adding that given the pace of recovery, Eskom would consider dialling down its power cuts by Monday.
Early on Monday morning, Eskom said the power outages would be reduced to Stage 4 until further notice.
Regular breakdowns at Eskom's fleet of ageing coal-fired plants, providing the bulk of electricity in Africa's most industrialised economy, are often the cause of load-shedding - an incremental system where Stage 1 sees 1,000 MW cut from the system, with Stage 6 the highest implemented to date.
Latest Stories
-
Jail corrupt officials in galamsey fight – Haruna Iddrisu to Judiciary
21 minutes -
Walewale MP dismisses forest mining ban as a superficial response to galamsey
33 minutes -
Chiefs must be central to galamsey fight – National House of Chiefs President
40 minutes -
Youth joblessness a security risk as 1.3m remain idle – Opare Addo
43 minutes -
You can’t levy athletes to Fund Sports Bill – Former Sports Minister
44 minutes -
Adu-Boahene trial: Testimony of prosecution witness favouring our defence – Atta Akyea
45 minutes -
Attorney-General lauds EOCO’s Executive Director
45 minutes -
Eastern Regional FDA undertakes operation against unregistered baby diapersÂ
48 minutes -
Local Government Ministry steps up unannounced sanitation inspections ahead of Christmas
53 minutes -
Parliament passes National Health Insurance Fund Amendment Bill
57 minutes -
Government remains unshakable in retooling security agencies – Interior Minister
1 hour -
 Unemployment eases to 12.8% in Q3 2025 – GSSÂ
1 hour -
Ablakwa commissions six new buses to ease transport burden of Foreign Affairs Ministry staff
1 hour -
Mahama pledges expanded support for exporters at GEPA awards
1 hour -
Vice President reaffirms government support for trade and industrial growth
1 hour