Audio By Carbonatix
Construction works on the Tema-Aflao highway resumed on April 7, 2025, after a 15-month suspension, but fresh concerns are emerging over delayed funding that could threaten the project’s smooth execution.
Contractor BHM International, responsible for the 17-kilometre stretch between the Kpone-Barrier and the Central University campus at Miotso, says the $105 million loan facility earmarked for the project has still not been reinstated.
Client Relations Manager at BHM International, Wisdom Adonoo, speaking to JoyNews after a visit to check progress of work warns that the longer the delay persists, the greater the risk of slowing down or even stalling progress which is scheduled for completion in 18 months.

“We are still waiting for the loan to be reinstated. In the meantime, we are working in good faith based on the minister’s assurance in April, and we are committed to delivering this project on time. But the longer the funds delay, the more difficult it becomes to execute the work as required by contract.”

A visit to the site shows significant improvements compared to five months ago. On the Tema-to-Aflao side, contractors have expanded the road by adding more lanes.

Most sections have already been filled and opened to traffic during peak hours, easing congestion that road users previously complained about.
On the Aflao-to-Accra side, excavation is still ongoing across several stretches, with heavy trucks and machinery actively at work.

BHM says the next phases include stabilisation, stone base pavement, asphalt, and pedestrian walkways, along with the completion of four planned flyovers, three of which already have structures erected.

Beyond funding, compensation for affected residents and traders remains a challenge. According to the Public Relations Officer Pastor Samson Allotey, out of 1,131 people identified for compensation, 842 have so far been paid, representing about 74.5%. Roughly half of those compensated have relocated to allow for construction, but the remaining yet to be compensated threatens work on section of the road.
“We urge government to expedite compensation for the remaining affected persons. Until payments are made and relocations completed, clearance for construction in some areas will remain an issue,” he said.
Latest Stories
-
Go back to the hand washing days – Ghanaians told
1 minute -
GoldBod commits GH¢35m to reclaim galamsey-damaged Tano Nimri Forest Reserve
6 minutes -
Afenyo-Markin reflects on loneliness of public service, says survival is largely spiritual
13 minutes -
Achimota Court designated to handle petroleum diversion cases – NPA CEO
21 minutes -
Bekwai court jails mine worker 14 years for defiling 8-year-old girl
26 minutes -
CHASS conference calls for collective action to tackle indiscipline in schools
30 minutes -
Oil edges down as investors weigh possible US sanctions on ‘shadow fleet’
43 minutes -
Netflix names former Disney executive Peter Rice as new content chief as Bajaria departs
53 minutes -
India’s ‘cockroach’ protesters set to return despite police crackdown
1 hour -
Porn showing choking or incest to be banned from early November, government says
1 hour -
Russell Brand accuser says he turned ‘monster-like’ before alleged rape
1 hour -
US police identify remains of man found in barrel in shrinking reservoir
2 hours -
My uncle told me I will never make it in music – Lojay
2 hours -
Martinez apologises for outburst and fined by Man Utd
2 hours -
Infantino apologises to FIFA Council – but told he is still not fit to lead
2 hours