The Ghana Grid Company Limited (GRIDCo) is installing a 66MVA transformer at its Anwomaso Sub-station to boost power supply in Kumasi and its surrounding areas.
The Director of Northern Network Services at GRIDCO, Mr Vincent Boakye, said the installation is expected to be completed by the end of this month, would complement the generating capacity of the four existing transformers at Ahodwo.
“We are having congestion on the line that transports power from Anwomanso to Ahodwo and beyond, and it is because we have not finished the 330 line that is supposed to link Kumasi to Kintampo,” he said.
Speaking to journalists after a tour of the Anwomaso Sub-station in the Oforikrom Municipality, Mr Boakye said electricity consumption had increased in Kumasi, necessitating the construction of transmission lines with bigger capacities.
“The transformer would, therefore, increase the power in the Greater Kumasi area and also reduce the amount taken from Anwomanso,” he added.
According to him, Kumasi was a big load centre, responsible for transmitting power to the northern parts of the country hence the need for a new transformer.
Mr Boakye said GRIDCO had also received a grant of 9.7 million Euros from the European Union to upgrade power generation in Kumasi.
Latest Stories
-
Ghana Immigration Service intensifies education on exploitation, abuse and trafficking in Aflao
15 minutes -
Supreme Court should have no cap on number of judges – Anthony Forson Jnr
15 minutes -
African journalists urged to frame, tell African stories positively
15 minutes -
Poor treatment of public servants affects quality of service – Former Civil Service chief
16 minutes -
Suspects detained beyond 48 hours can sue police for redress – Justice Amoako Asante
16 minutes -
Convicted Bosnian Serb war criminal Mladić dies aged 84
20 minutes -
Ga Mantse boosts Sacred Crown Awards, names Princess Duncan as CEO to drive global push
20 minutes -
At least 12 dead, 54 injured as wildfires sweep through northern Algeria
21 minutes -
AI cannot replace lawyers and judges – Justice Asante
27 minutes -
PURC intervention restores power to Abofour-Dumasua community
29 minutes -
Africa needs 35% more to recruit health workers as 1 in 5 health dollars is wasted – WHO
30 minutes -
African Pension Funds shift more capital into private equity
32 minutes -
PURC engages Abofour-Dumasua residents over quality-of-service concerns amid faulty transformer
33 minutes -
AES, Ghanaian youth to confront debt, reparations at Accra forum
45 minutes -
Domestic Gold Purchase Programme: ‘US$1.7bn loss is largely a book issue’ — IEA
46 minutes