The board and management of the Komfo Anokye Teaching Hospital (KATH) in Kumasi have expressed worry over the continued delay in the completion of works on a sickle cell and blood center project for the hospital.
Construction works on the project, which is being sponsored by the Sickle Cell Foundation of Ghana (SCFG) with funding from the Ghana National Petroleum Corporation (GNPC), have come to a halt for more than two years.
The project was to be completed in May 2019 but had to be extended for one year to May 2020.
So far, the first fixing of the plumbing and electrical works have been completed and the building of the basement structure and ground floor has also been finished.
However, further works on the project have been aborted because the contractor had not been paid since August 2020 and at the end of the year 2021, the project was still behind schedule.
This came to light when the Chief Executive Officer of KATH, Dr Oheneba Owusu-Danso, led members of the KATH Board to visit some of the hospital projects under construction.
The visit was to allow the board members to acquaint themselves with the progress of work on the projects and the challenges facing the contractors.
Nana Asibey Opoku, Consultant to the project, told the team that since August 2020, no payment had been made to the contractors, thus accounting for the stalling of the project.
He said the Foundation had lobbied the Asantehene, Otumfuo Osei Tutu II, to press on the GNPC to release funds for the completion of the project.
The GNPC, through the Asantehene in 2016, presented a cheque for $4.5 million to the Sickle Cell Foundation for the construction, tooling, and training of the personnel for the first-ever Sickle Cell and Blood Centre in Ghana at KATH.
Members of the KATH Board who were visibly worried about the situation expressed grave concerns about the delay of the project and said it could affect the cost of the project and further delay its completion.
The board appealed to the GNPC to honour its pledge and pay the contractor to enable them to complete the project.
When completed, the center will serve as a one-stop for the management of all sickle cell cases and blood transfusion-related services for the northern half of the country.
Latest Stories
-
Create open African market to accelerate connectivity – Telecel Business Director
6 minutes -
Gold Fields Lease Renewal: Why the IEA’s case for resource nationalism fails the reality rest
12 minutes -
Ghana Sports Fund unveils ambitious plan to transform sports development nationwide
12 minutes -
Ghana Sports Fund to porioritise grassroots sports, talent identification and infrastructure development
16 minutes -
Ghana Sports Fund engages stakeholders on revenue mobilisation, transparency and sustainable sports financing
18 minutes -
Albert Bondah named Media & PR Manager for 2026 Ghana Comedy AwardsÂ
23 minutes -
NPP questions Circuit Court 9 ruling in Abronye DC case
24 minutes -
Artificial Intelligence researcher urges responsible AI use at high-level United Nations Forum
28 minutes -
Augustine Boakye to miss Black Stars friendly against Mexico
32 minutes -
Zoomlion Kenya begins major transformation of Nairobi waste management system
33 minutes -
NPP calls on diplomatic community to protect freedoms, end political prosecutions in Ghana
58 minutes -
NPP Youth Organiser warns of ‘ungovernable’ response over alleged harassment of members
1 hour -
Climate change: Africa must move adaptation from promises to action – AGN Chair urges
1 hour -
Traders raise fresh concerns over stalled Takoradi Market Circle redevelopment project
2 hours -
Lovebirds in NDC politics? Dafeamekpor’s birthday message to Ebi Bright sets social media ablaze
2 hours