Finance Minister Ken Ofori Atta has provided a list of roads, interchanges and bridges under various stages of completion across the country.
Delivering the Mid-Year Budget Review, on Monday, he noted that this forms part of the government’s commitment to improving mobility and accessibility as well as safety along major trunk roads.
“Government remains committed to improving road infrastructure in line with the fiscal consolidation plan in the IMF-backed PCPEG and in partnership with the private sector,” Mr Ofori Atta said.
Below is the list of roads and bridges under construction;
1. Works on the 31.2km Assin Fosu-Assin Praso portion of the National Trunk Road N8 (Phase 2) - was completed and commissioned in June 2023;
2. Accra-Tema Beach Road (Lot 1 and Lot 2) - 79 per cent and 89 per cent complete respectively;
3. Construction of a 3-tier interchange at Nungua Barrier - is ongoing;
4. Development works on the Kumasi Lake Road and Drainage Extension project - is 98 per cent complete;
5. Selected Roads in Sekondi and Takoradi Phase 1 - is 21 per cent complete;
6. Tema-Aflao road - is 30 per cent complete;
7. Nsawam-Ofankor road - is 26 per cent complete;
8. Reconstruction of Bechem-Techimantia-Akomadan road - is 64 per cent complete;
9. Reconstruction of Agona Nkwanta-Tarkwa road - is 34 per cent complete;
10. Phase 2 of the Obetsebi Lamptey Circle Interchange and other ancillary works - is 86 per cent complete as of June 2023;
11. Construction of a 4-tier interchange at Suame in the Ashanti Region - has commenced;
12. Construction of 50 prefabricated bridges in all sixteen regions continued in 2023 and are 86 per cent complete as of the end of June;
13. Design, fabrication and delivery of 87 No. steel panel bridges - is ongoing, with 45 bridges delivered;
14. New bridge under construction at Twifo Praso to separate vehicular traffic from the railway line - is 93 per cent complete.
Aside from these, Mr Ofori Atta said that two projects are at different stages of preparation under the Road Sector’s Public Private Partnerships (PPP) programme for the financing, construction and management of road infrastructure.
They are;
- Phase 1 of the Accra-Tema Motorway Extension Project (31.7km) involves the reconstruction of the Motorway. The Concession Agreement and draft Engineering Procurement and Construction (EPC) agreement have been finalised and will be laid in this House.
- The Development of Tema Arterial Roads will be structured on a PPP basis using the Build Operate and Transfer (BOT) model. The appraisal of the project is ongoing.
The Finance Minister added that the government will also embark on a community road improvement programme to increase productivity and facilitate the transportation of food crops.
“Districts Assemblies will be given complementary equipment to ensure that their local roads are motorable throughout the year,” he explained.
Latest Stories
-
Failure is part of Success — Peter Debrah encourages resilience among Students
3 hours -
Is the IMF Complicit in Bank of Ghana’s Massive 2025 Losses? – IERPP
4 hours -
Scaling Together: Prudential Bank MD’s advice on fintech‑bank partnerships in Africa
5 hours -
Joe Mettle inspires hope with new song ‘This Year’
5 hours -
Antisemitism ‘allowed to come into the open’ says Bondi victim’s daughter
6 hours -
What Is Wrong with Us? Why do we Reject Colonialism yet Cling to its Titles?
6 hours -
World Bank pushes regional health strategy to close financing gaps in West and Central Africa
6 hours -
Britney Spears pleads guilty to reckless driving after arrest
6 hours -
Parentage, not paternity: Ghana’s proposed compulsory paternity testing bill sparks fears of discrimination against mothers
6 hours -
Samsung family pays off record $8bn inheritance tax bill
6 hours -
Spain seizes record amount of cocaine in Atlantic Ocean, authorities say
6 hours -
Two killed and many injured after car driven into crowd in German city of Leipzig
6 hours -
KiDi drops ‘Signature’ with Lasmid ahead of album release
6 hours -
UAE accuses Iran of renewed drone and missile attacks
6 hours -
Giuliani recovering from pneumonia and ‘now breathing on his own’
7 hours