Parliament has approved a $243.6 million facility to procure a total of 35 standard gauge rolling stock as part of government's efforts to revamp the railway sector.
The supplier’s credit agreement is between government represented by the Finance Ministry and Messrs Dongfang Electric International Corporation.
The purpose of the instant credit agreement is to finance the acquisition of standard gauge rolling stock to enable testing, commissioning, and immediate operation of the new standard gauge railway lines currently under construction in the country.
The scope of work between the partners is to supply nine Nos. 4500HP Mainline Diesel Locomotive with a maximum speed of 160km/h for passengers, the supply of 48 Nos. Passengers coaches, 15 Nos. 4500HP Mainline diesel locomotives for freight with a maximum speed of 100km/h.
The rest also includes the supply of 330 Nos. Freight Wagons and supply of 11 Nos. 1000HP Shunting Diesel Locomotives.
A total of 35 standard gauge trains are therefore to be delivered by the suppliers as part of the contract.
The contract will be implemented in two phases. The first phase will be completed in two batches within 12 months and 18 months respectively from the date of contract commencement.
Per the agreement, Messrs. Dongfang Electric International Corporation will be procuring the 100% financial solution to execute the contract from the Industrial and Commercial Bank of China (ICBC) Limited or China Construction Bank.
The terms and conditions of the agreement is two years grace period and 10 years of repayment period. The interest rate of the facility is 6M Libor +2.5% p.a. with 12 years tenor.
Presenting the Finance Committee’s report for approval of the agreement, Chairman of the Committee, Dr. Mark Assibey Yeboah observed that as part of the agreement, the company will also provide spare parts and tools along with a 24 months warranty period.
He added that the contract will see the establishment of one Maintenance Workshop (not more than 3000m2) with equipment at a location yet to be determined by the purchaser.
Dr Assibey added that the supplier will also provide training for skilled personnel or railway engineers and managers in all aspects of the rolling stock systems including Locomotive design, operation, and maintenance to ensure adequate transfer of technology from the suppliers to the local staff.
On the socio-economic impact, the Chairman said, the operations of the trains will facilitate the movement of people and goods and create both direct and indirect employment opportunities and generate income within the catchment communities.
The committee also observed that the construction of the 97km railway line from Port of Tema to Mpakadan is expected to be completed ahead of the contractual completion date of July 2021 and some of the rolling stock being financed under the instant Supplier’s Credit Agreement will be used to test, commission and operationalise the Tema-Mpakadan rail line.
Debating the facility for approval from the House, the minority Spokesperson on Roads and Transport, Governs Kwame Agbodza demanded a Value for Money (VfM) assessment on the agreement in accordance with the laws of Ghana.
He, however, added that smooth implementation of the facility will boost the railway sector of the economy.
Latest Stories
-
Okraku credits Black Princesses technical team for Korea Win
4 minutes -
U20 Women’s World Cup: Bjorkgren hails Black Princesses’ win over Korea
14 minutes -
Man found dead in suspected suicide at Assin-Amoabeng
19 minutes -
ODRO’S Foundation supports persons living with disabilities in Cape Coast
28 minutes -
Saalim Bamba suspends NPP Nasara campaign after convoy accident
39 minutes -
CDD-Ghana pushes for independent authority to regulate political financing
47 minutes -
Ghana music industry needs collective public-private investment – UK High Commissioner
1 hour -
“We don’t have the mindset of sabotage” – NPP on MMDCE election proposal
1 hour -
From Kumasi to the world: Mirakilouz Beatz’s rise in music production
2 hours -
Low pay making it harder for universities to attract PhD holders – UTAG-UG
2 hours -
Richard Nii Armah Quaye, Ga Mantse to launch scholarship scheme for Ga-Dangbe students
2 hours -
Julius Emunah parts ways with Hearts of Oak as Managing Director
2 hours -
Weija Dam flooding will persist without political will to relocate residents – NADMO
2 hours -
UMB, 3TREES launch paint outlets across constituencies ahead of Ghana’s 70th anniversary
2 hours -
CSSPS: Education Ministry orders action against alleged payment demands in Ashanti Region
2 hours