The Roads and Highways Minister, Governs Kwame Agbodza, has dismissed criticism of the redesign of the Suame Interchange, insisting the controversy is political rather than based on engineering considerations.
Speaking on Joy News’ PM Express on Tuesday, he explained that the project stalled due to funding challenges and unpaid contractor debts.
“It stalled because, you remember, we started a project and it was supposed to be a commercial loan, then we couldn’t draw down, then we had an opportunity to take a $750 million Afri Exim Bank loan,” he said.
He noted that part of the funds was redirected to support interchange works, but the project eventually halted.
“But it stopped because we owed the contractor in excess of $23 million for work done and not paid for,” he added.
The Minister said the original design aimed to ease congestion at Suame Roundabout, a key traffic point on the Kumasi corridor.
“Now, if you watch the way Kumasi works, the bulk of the traffic going through the central corridor… will now have to drive to Suame roundabout currently, and fight the local traffic to get out of that,” he explained.
He revealed that the initial plan was to construct a multi-tier interchange to manage traffic flow, but broader traffic realities required a rethink.
“So initially the design was to have a three-tier and four-tier… but if you notice what we were doing, we could have, we could actually do the grade separation. But beyond that, they get stuck, because on the Mampong road, there’s no work going on there, so the traffic was still going to build up,” he said.
According to him, a more effective solution is to divert traffic away from Kumasi altogether.
“So the right thing to do, actually, was to do a diversion at around Ejisu, so to bypass Kumasi completely… so that if you were to be going to Tamale, there’s no need for you to come and struggle at Suame interchange,” he stated.
He argued that with such a bypass, the need for a four-tier interchange becomes questionable.
“As a result, you don’t need all four interchanges to do it… We probably don’t need the four-tier. We probably can reduce to three tiers,” he said.
The Minister further disclosed that land acquisition challenges also complicated the project.
“…there was a part of the area which we needed to build, the fourth tier… which was not land that we already own… later, I’m told that the lawyers wrote and said that they want over GH¢100 million as compensation, which was not part of the project,” he said.
Responding to criticism from his predecessor, Francis Asenso-Boakye, and the Ashanti caucus, who argue the redesign could worsen congestion, Mr Agbodza rejected the claims.
“It has nothing to do with engineering. It’s pure politics,” he said.
He added that the new plan will still deliver a technical solution to traffic challenges.
“I can guarantee you what we want to do will be an engineering solution,” he stressed.
The Minister also insisted that no funds are being diverted away from the project.
“No one is taking one cedi out of the project. Whatever savings are made out of not building the fourth tier will be applied to… building the road from the interchange towards Mampong, which is a road in a very terrible situation currently,” he said.
Latest Stories
-
CCCFS praises EPA Ghana for publishing 233 EIA reports, urges deeper access at district level
6 minutes -
Ghanaians should be advised against non-essential travel to South Africa – Minority
9 minutes -
Government lifts curfew on Gushegu District communities following improved security
11 minutes -
NACOC intercepts 5 million opiod tablets of tapentadol in major drug bust
15 minutes -
Ghana engages American aircraft manufacturer Boeing in renewed push to relaunch national carrier
19 minutes -
Leadership at Beloved Tanyigbe: Togbe Etoi Kodzo II speaks on his 9th Anniversary of Enstoolment
20 minutes -
E&P’s gold sale vindicates Damang bid – Sammy Gyamfi
23 minutes -
Employers urged to use AI to improve safety workplace
23 minutes -
NDPC chair calls for creation of auto zones to restore spatial planning discipline
23 minutes -
Lightwave sues Health Minister over alleged ‘false and damaging’ remarks, demands apology
25 minutes -
Witties Ghana signs Ghana most Beautiful’s Sarfoa as influencer for Clinell Wipes
28 minutes -
Students displaced after storm rips off school roof in North Tongu
36 minutes -
E&P’s 100% gold sale to GoldBod sets benchmark — Legal Rep
38 minutes -
Photos: Mahama visits Akosombo Dam, calls for upgrade after fire incident
42 minutes -
Damang Mine sells 100% of first gold output to GoldBod, BoG in historic move
43 minutes