The Foreign Affairs Ministry said a project that was initially supposed to cost government GH¢1,435,728.99 was executed at GH¢7,967,886.57 because the contractor did not execute on time due to ill health.
The contract for the rehabilitation of Adu Lodge Guest House was awarded to International Development Resources on March 15, 2007.
But according to the Acting Chief Director of the Ministry, Ambassador Ramses Joseph Cleland, the project came to a grind a year later due to the ill health of the contractor.
Appearing before the Public Accounts Committee (PAC) on Friday, January 20, 2023, the Ministry said the project was revisited in March 2019 and upon the request of the consultant, was re-valued to GH¢7,967,886.57 for the same contractor to execute.
The Auditor General's report noted that, as of June 2019, a total of GH¢7,741,501.60 (representing 90% of the contract sum) had already been paid.
According to the Ministry, the project has finally been completed and handed over to the Ministry, after 13 years of delay.
Unsatisfied with the explanation from the Ministry's explanation, the committee queried whether the terms of the contract allowed for the inability of the contractor to execute the project in due course, to come at a cost to the state.
The Ministry in response said they were unable to speak to that except the estate officer, who was not present at the committee sitting.
The committee has therefore directed the Ministry to furnish the Public Accounts Committee with the contract and all necessary documents for a determination on the matter in its report.
Latest Stories
-
National Justice Conference calls for sustainable funding to combat child labour exploitation
19 seconds -
Bank of Ghana Partners DASA 2026 to advance Digital Asset regulation and innovation
3 minutes -
ECG and 9 state institutions failed to pay over ¢3bn in taxes in 2024, driving record ¢5.2bn irregularities – Auditor-General
6 minutes -
MMDAs prioritising permit fees over proper planning enforcement – Physical Planners Association President
17 minutes -
Nkwanta-Dadiase road rehabilitation underway after years of neglect
20 minutes -
Slight coastal rain, evening thunderstorms expected across parts of Ghana – GMet
38 minutes -
Former Dormaa East MP calls for greater investment in flood prevention infrastructure
39 minutes -
The smartest $130,000 property investment in Accra at the moment
45 minutes -
Bond market: Turnover increased by 56% to GH¢2.44bn
1 hour -
MDA financial irregularities surge 156% to GH¢5.27bn in 2025 — Auditor-General
2 hours -
Gov’t prioritising flood response PR over prevention – Former Dormaa East MP
2 hours -
High court dismisses Kwame Baffoe’s bid to strike out defamation suit by Dr Ransford Abbey
2 hours -
Government spending in quarter one 2026 dropped by 21%; capital expenditure still below target
2 hours -
Tax revenue and grants for quarter one 2026 falls to GH¢57.5bn
3 hours -
Ghana rejects Ramaphosa state visit request over xenophobic attacks, concerns about his safety
3 hours