The Foreign Affairs Ministry said a project that was initially supposed to cost government GH¢1,435,728.99 was executed at GH¢7,967,886.57 because the contractor did not execute on time due to ill health.
The contract for the rehabilitation of Adu Lodge Guest House was awarded to International Development Resources on March 15, 2007.
But according to the Acting Chief Director of the Ministry, Ambassador Ramses Joseph Cleland, the project came to a grind a year later due to the ill health of the contractor.
Appearing before the Public Accounts Committee (PAC) on Friday, January 20, 2023, the Ministry said the project was revisited in March 2019 and upon the request of the consultant, was re-valued to GH¢7,967,886.57 for the same contractor to execute.
The Auditor General's report noted that, as of June 2019, a total of GH¢7,741,501.60 (representing 90% of the contract sum) had already been paid.
According to the Ministry, the project has finally been completed and handed over to the Ministry, after 13 years of delay.
Unsatisfied with the explanation from the Ministry's explanation, the committee queried whether the terms of the contract allowed for the inability of the contractor to execute the project in due course, to come at a cost to the state.
The Ministry in response said they were unable to speak to that except the estate officer, who was not present at the committee sitting.
The committee has therefore directed the Ministry to furnish the Public Accounts Committee with the contract and all necessary documents for a determination on the matter in its report.
Latest Stories
-
Ghana makes history with international karting debut
28 minutes -
Livestream: The Law discusses new road traffic rules
54 minutes -
What’s driving men to get penis fillers, despite the risks?
56 minutes -
The world’s oldest president left for a ‘brief stay’ in Europe, he hasn’t returned in two months
1 hour -
Trapped driver rescued after accident on Kintampo–Tamale highway
2 hours -
Civil Service must put citizens at centre of decision-making – Vice President
2 hours -
Firefighters battle blaze at Accra New Town apartment
2 hours -
Ghana receives five new envoys to strengthen diplomatic relations – Ablakwa
2 hours -
Europe’s tallest Virgin Mary statue unveiled in rural Poland
2 hours -
Sammi Awuku denies reports of EOCO arrest
2 hours -
Stonebwoy makes history at OVO Arena Wembley with monumental BHIM Festival
3 hours -
Qatar denies capturing three Iranian pilots after downing fighter jets
3 hours -
Tano North chiefs petition Mahama over galamsey destruction in River Tano
4 hours -
Kalpohin SHS, NOBISCO qualify to represent Northern Region at National Public Speaking Competition
4 hours -
Missing records of illegal gold purchases in Ghana raise concern – Duncan-Williams
4 hours