A routine monitoring tour by the Minister for Roads and Highways, Kwame Governs Agbodza, turned tense on Monday after he discovered minimal progress on the Techiman–Wenchi road project, despite the release of GH¢66 million in mobilisation funds.
The minister, accompanied by his deputy and the Bono East Regional Minister, expressed strong dissatisfaction after observing that, five months after payment, the contractor had only carried out surface vegetation clearing on the project.
“Look at this. Five months. Sixty-six million Ghana Cedis. What do we have? Surface clearing. No gravel, no drainage, no structure,” an agitated Minister Agbodza said on site. “This is unacceptable. Absolutely unacceptable.”

According to documents reviewed during the tour, the contractor received the mobilisation funds late last year to facilitate the early commencement of works. However, the minister noted that the contractor appeared to be working outside the agreed project timeline.
Deputy Roads Minister Suhuyini emphasised that mobilisation funds are not a grant but a performance-based advance meant to accelerate work, not delay it.
The contractor has been summoned to appear before the ministry on Thursday, 7 May 2026. The minister warned that failure to demonstrate the capacity to execute the project could result in termination of the contract.
“If you cannot do the work, we will find someone who can. The President has a vision. We will not allow any individual to derail the Big Push,” he stated. “A new contractor will be appointed if necessary.”

The Bono East Regional Minister also expressed disappointment at the pace of work and announced plans for regular, unannounced monitoring exercises to enforce accountability across all road projects in the region.
“All road contractors in this region must take caution and ensure the right things are done as per their contracts, or risk losing their contracts immediately,” he warned.
He added that technical audits would be conducted on all ongoing projects to prevent delays and ensure compliance.

Meanwhile, residents and road users along the Techiman–Wenchi–Sawla corridor have welcomed the minister’s intervention, expressing frustration over the prolonged delay.
“They came, they cut the grass, and we thought work would start. That was months ago,” a trader said anonymously. “We pray the minister’s words today will become action.”
The ministry is expected to take further action following the contractor’s appearance, as attention turns to whether the project will be reassigned or accelerated under stricter supervision.
Latest Stories
-
Black Stars: We need to be more aggressive with officials – Semenyo
17 minutes -
Seychelles primed for 69th UN Tourism CAF Summit as Golden Jubilee celebrations commence
40 minutes -
KAIPTC marks 15th Graduation Ceremony with call for peace and security leadership
44 minutes -
World Drug Day: Bel-Aqua Foundation donates GH¢120,000 to NACOC to combat drug abuse in SHSs
48 minutes -
When African States walk away from the ICC, victims pay the highest price
52 minutes -
Kenpong Travel disputes First Atlantic Bank’s winding-up move over alleged GH¢2.5m debt
1 hour -
Dr Tengol K. Kplemani appointed Africa Ambassador by global tourism network
2 hours -
Reversing utility tariff hikes might be difficult – PURC
2 hours -
Reggae legend Brinsley Forde announces new single ‘Ites Gold & Green’
2 hours -
Gyakie releases new single ‘Treasure’
2 hours -
Justice Mensa-Bonsu warns of changing face of warfare, rising extremism and threats to global peace
2 hours -
Uncontrolled hypertension can lead to erectile dysfunction —Urologist
2 hours -
Over 200 music industry stakeholders attend 27th TGMA Music Summit to explore brand partnerships and music contracts
2 hours -
Deputy Health Minister calls for nationwide support for Ghana Medical Trust Fund
2 hours -
GMTF engages Regional Ministers to deepen nationwide awareness campaign
2 hours