A routine monitoring tour by the Minister for Roads and Highways, Kwame Governs Agbodza, turned tense on Monday after he discovered minimal progress on the Techiman–Wenchi road project, despite the release of GH¢66 million in mobilisation funds.
The minister, accompanied by his deputy and the Bono East Regional Minister, expressed strong dissatisfaction after observing that, five months after payment, the contractor had only carried out surface vegetation clearing on the project.
“Look at this. Five months. Sixty-six million Ghana Cedis. What do we have? Surface clearing. No gravel, no drainage, no structure,” an agitated Minister Agbodza said on site. “This is unacceptable. Absolutely unacceptable.”

According to documents reviewed during the tour, the contractor received the mobilisation funds late last year to facilitate the early commencement of works. However, the minister noted that the contractor appeared to be working outside the agreed project timeline.
Deputy Roads Minister Suhuyini emphasised that mobilisation funds are not a grant but a performance-based advance meant to accelerate work, not delay it.
The contractor has been summoned to appear before the ministry on Thursday, 7 May 2026. The minister warned that failure to demonstrate the capacity to execute the project could result in termination of the contract.
“If you cannot do the work, we will find someone who can. The President has a vision. We will not allow any individual to derail the Big Push,” he stated. “A new contractor will be appointed if necessary.”

The Bono East Regional Minister also expressed disappointment at the pace of work and announced plans for regular, unannounced monitoring exercises to enforce accountability across all road projects in the region.
“All road contractors in this region must take caution and ensure the right things are done as per their contracts, or risk losing their contracts immediately,” he warned.
He added that technical audits would be conducted on all ongoing projects to prevent delays and ensure compliance.

Meanwhile, residents and road users along the Techiman–Wenchi–Sawla corridor have welcomed the minister’s intervention, expressing frustration over the prolonged delay.
“They came, they cut the grass, and we thought work would start. That was months ago,” a trader said anonymously. “We pray the minister’s words today will become action.”
The ministry is expected to take further action following the contractor’s appearance, as attention turns to whether the project will be reassigned or accelerated under stricter supervision.
Latest Stories
-
‘We survived on snow and sand’ – Victim recounts harrowing experience on frontlines of the Russia-Ukraine war
6 minutes -
‘I considered retiring’ – Kofi Kyereh opens up on rehabilitation struggles
11 minutes -
Gov’t and mining companies in talks over gold mobilisation and forex strategy
14 minutes -
Gender Ministry rallies support for Ghana’s bid to UNCRPD Expert Committee seat
15 minutes -
WPL 2025/26: Hasaacas Ladies receive donation from Betika Ghana after second-place finish
18 minutes -
Adamus CEO Angela List rejects illegal mining claims, says company has no link to galamsey
28 minutes -
From crisis to confidence: Ghana’s remarkable economic turnaround
29 minutes -
Youth employment drive gains traction as partnerships scale across Africa
29 minutes -
Election 2028: Asiedu Nketia closes gap on Bawumia – Global Info Analytics
33 minutes -
EU–Ghana relations enter new phase focused on stability and mutual interests
33 minutes -
‘I’m striving to play at the 2026 World Cup’ – Kofi Kyereh
35 minutes -
Global Info Analytics: Bawumia’s base solid, but swing voters favour NDC
40 minutes -
Global Info Analytics: 2024 Absentee voters tilt heavily toward NDC
54 minutes -
Ghana’s AI future will be decided by infrastructure, not ambition
55 minutes -
Amin Adam calls for IMF action on BoG recapitalisation, gold sales and monetary risks
1 hour