The reconstruction of the Accra-Tema Motorway is 48% complete, with major drainage infrastructure already helping to reduce flooding along the corridor, according to road construction consultant Ing. Kwabena Bempong.
Ing. Bempong said work is currently focused on the urban highway, which will function as a service road alongside the main motorway.
"We're currently working on the urban highway, which is more like a service road. We're currently around 48%; we have not yet gone halfway through," he told host Bernard Avle.
He explained that a significant portion of the project has centred on drainage infrastructure and interchange construction to address the perennial flooding that has affected sections of the motorway.
"The challenges we have had mainly were the various diversions around the interchanges and the drainage structures," he said.
According to Ing. Bempong, the project involves the construction of about 20 culverts and three interchanges, with most of those structures now nearing completion.
"We have about 20 culverts and three interchanges; we have constructed lots of them, and the majority are almost done, and that has reduced the flooding; we didn't experience that," he said.
He added that contractors have prioritised keeping the motorway open to traffic while construction continues.
"We make sure the road is passable throughout the period of construction," he stated.
He spoke on The Point of View on Channel One TV on Monday, July 13,
The update comes after recent flooding in parts of the country that claimed lives, displaced residents and submerged homes, prompting renewed attention on drainage infrastructure and flood mitigation.
In response to the disaster, President John Dramani Mahama directed a nationwide clean-up exercise, which took place on Friday, July 10, and Saturday, July 11. The exercise brought together the President, government officials and members of the public to desilt drains, clear choked gutters and clean streets in flood-affected communities as part of efforts to improve sanitation and reduce the risk of future flooding.
Latest Stories
-
NSMQ 2026: Kpando SHS brush aside Abor, Jukwa to storm One-Eighth stage with 32 point gap
21 minutes -
Duncan Amoah: Gov’t should create conditions for 24-hour economy, not build markets
27 minutes -
JoyNews-Republic Bank Habitat Fair finale turns homeownership dreams into real possibilities
1 hour -
Bamiri chief commissions KG block, guest house to boost education and revenue
1 hour -
NSMQ 2026: Yaa Asantewaa Girls’ going ‘beck’ to Tanoso after Bishop Herman deals them early exit
2 hours -
Data Protection Commission acquires two vehicles to strengthen data protection enforcement
2 hours -
NSMQ 2026: Holy Child School storms back from two-year NSMQ absence to book One-Eighth ticket
3 hours -
GNFS dismisses reports of unpaid 2025 rent allowance
5 hours -
Gordon Asare-Bediako steps down from NPP Communications Director race, backs Dennis Aboagye
5 hours -
GES dismisses requirement for newly promoted teachers to submit documents for salary adjustments
5 hours -
Meko Bono 2026: Vice President pledges agricultural revival as Atebubu hosts grand homecoming
6 hours -
Russian skydiver Sergey Boytcov sets world record with 11,551-metre stratosphere jump
6 hours -
Ablakwa-led committee submits five reports to Mahama ahead of 2027 AU chairmanship
6 hours -
Africa not seeking Western cash in reparations campaign – Ablakwa
6 hours -
Production decline, reserve depletion threaten Ghana’s upstream sector – Jinapor
6 hours