Civil works on three of the Agenda 111 health projects commissioned under Akufo-Addo are yet to be completed.
Though facilities at Trede, Oforikrom and Ahanta West Districts were commissioned two days before the 2024 elections, there were no plans in place for handing over to the Ghana Health Service for operationalisation.
Health Minister, Kwabena Mintah Akandoh says civil works for all the facilities are below ninety-five percent complete.

“In terms of the civil works, none of the commissioned facilities is above ninety five percent and I am being very charitable”, he said.
The Health Minister made this statement after touring the two commissioned Agenda 111 facilities in the Ashanti Region.
According to the Health Minister, only 400 million dollars of the 1.7 billion dollars needed for the 111 health facilities was released for construction.

By the figures, over a billion dollars will be needed for the completion of all facilities under construction.
“We need not less than 1.4 billion dollars to be able to finish the projects, these are the facts”, Mr. Akandoh explains.
A visit to the Oforikrom and Atwima Nwabiagya facilities, commissioned by the former President showed both facilities are not operational.
Road networks leading to both sites untarred, dusty and bumpy.

At the Trede facility, part of the roads within the hospital are untarred. Though civil works are advanced, there is much to be done in both facilities.
At Trede, some beds and a few equipment that were moved into the hospital continue to gather dust due to inactivity.
Mr. Akandoh explains, “Per my inspection, the civil works are not complete. Labs are incomplete, not all equipment have been delivered so we don’t have health workers here as expected.”

“I came with the Director General of the Ghana Health Service and the Regional Director, they tell me there is no action plan for recruitment or staffing for these facilities”, he added.
According to the Minister, though there are no dedicated source of funding for the project, the government is willing to complete the projects following submission of a blueprint.
Latest Stories
-
Domestic violence case: John Odartey Lamptey remanded over alleged brutal assault on wife
5 minutes -
Minority urges government to tackle smuggling and protect local farmers
7 minutes -
Ashanti regional minister drags Democracy Hub member to court over alleged galamsey remarks
9 minutes -
Mineral royalties surge across all sub-sectors in 2025; record strong gains in gold, manganese
10 minutes -
Police arrest five suspects behind robberies in Sefwi Bekwai
10 minutes -
Ghana’s economy to expand marginally to 5.9% in 2026 – Fitch Solutions
11 minutes -
Newage Agric Solutions donates rice, soybean oil and cash to MoFA for farmers’ day
12 minutes -
Analysis: After allocating over ₵1bn, parliament now turns on the OSP
50 minutes -
OSP’s failure to stop Ofori-Atta is an irrecoverable mistake – Kpebu
1 hour -
UPSA confers posthumous honorary doctorate on former first lady Nana Konadu Agyeman-Rawlings
1 hour -
Martin Kpebu says he has not been formally charged by OSP
1 hour -
Why not clean energy: Cost or access?
1 hour -
Minority sounds alarm over fuel shortages crippling Ghana’s fishing communities
1 hour -
Minority calls for urgent action to shield farmers from rising production challenges
1 hour -
AGRA Ghana salutes Farmers as nation marks Farmers’ Day
2 hours