President Nana Akufo-Addo has inspected ongoing work on the construction of the Kumasi International Airport, which, according to the contractor, is currently 77% complete, and is expected to be completed in June 2022.

President Akufo-Addo visited the site of the construction on Friday when he commenced his four-day working visit to the Ashanti Region, as part of his annual working visits to all the regions of the country.

On June 6, 2018, the President cut the sod for the commencement of work on Phase Two of the Kumasi Airport Project, where he indicated that “the expansion of this airport is a critical part of government’s vision to expand the frontiers of the aviation industry in the country and to realise the dream of making Ghana an aviation hub in West Africa.”

Inspecting work on the site, the President was told that the terminal building was 88% complete, the road network 93% complete, the Apron 89% complete, with the air traffic control and rescue and firefighting services 53% complete.

The scope of work includes the extension of existing runway pavement from 1,981 metres to 2,320 metres, the construction of a new taxi link and apron, two new apron parking stands, aeronautical ground lighting systems, the design and building of a terminal with the capacity to handle 800,000 passengers per annum, an 11 MW substation, as well the provision of new bulk utility (electricity, water, sewage treatment system, internet etc.) services, independent of the existing utility services for the existing airport facilities.

Phase three of the project involves the construction of the air traffic control building, a fire building station, as well as the expansion of the existing runway pavement. The construction of the fuel farm is to be funded by GOIL.

With the project being constructed by Messrs. Contracta Construction UK Limited, the total project sum is €124.9 million, with financing from Santander, Deutche Bank, and UKEF.

President Akufo-Addo expressed satisfaction with the progress of work undertaken so far, and charged the Ministry of Transport as well as the Contractor to ensure that the October 2022 deadline for completion is met.
Latest Stories
-
World Relays 2026: Ibrahim Fuseini details how he missed flight to Botswana
12 minutes -
Kobby Kyei heads to Nairobi for Africa Forward Summit 2026
12 minutes -
What to know about hantavirus, suspected virus outbreak on Atlantic cruise shipÂ
15 minutes -
Education Minister directs GES to reserve recruitment quota for persons with disabilities
18 minutes -
International Schools Tennis tournament uncovers young talent in Accra
21 minutes -
Mahama rallies chiefs, security agencies against rising drug abuse among youth
24 minutes -
Lifeline for Afife R/C Primary School as JOBerg supports GETFund with GH¢2.25m for classroom and toilet project
24 minutes -
Josh Blakk drops live EP as he eyes Best Male Vocal honour at TGMA
25 minutes -
Beyond the headlines: Rethinking emergency care in Ghana
28 minutes -
Ghana facing moral decline in leadership across institutions – Prof Karikari
29 minutes -
Play House: DJ Mensah launches state-of-the-art recording studio in Accra
38 minutes -
Education Minister calls on WAEC to review its mode of transporting examination materials
41 minutes -
Asantehene honours Angela List
48 minutes -
Fate of OSP, future of anti-corruption mandate
51 minutes -
Auto Bridge Ghana enters market to simplify vehicle importation and sales
1 hour