Audio By Carbonatix
President Nana Akufo-Addo has inspected ongoing work on the construction of the Kumasi International Airport, which, according to the contractor, is currently 77% complete, and is expected to be completed in June 2022.

President Akufo-Addo visited the site of the construction on Friday when he commenced his four-day working visit to the Ashanti Region, as part of his annual working visits to all the regions of the country.

On June 6, 2018, the President cut the sod for the commencement of work on Phase Two of the Kumasi Airport Project, where he indicated that “the expansion of this airport is a critical part of government’s vision to expand the frontiers of the aviation industry in the country and to realise the dream of making Ghana an aviation hub in West Africa.”

Inspecting work on the site, the President was told that the terminal building was 88% complete, the road network 93% complete, the Apron 89% complete, with the air traffic control and rescue and firefighting services 53% complete.

The scope of work includes the extension of existing runway pavement from 1,981 metres to 2,320 metres, the construction of a new taxi link and apron, two new apron parking stands, aeronautical ground lighting systems, the design and building of a terminal with the capacity to handle 800,000 passengers per annum, an 11 MW substation, as well the provision of new bulk utility (electricity, water, sewage treatment system, internet etc.) services, independent of the existing utility services for the existing airport facilities.

Phase three of the project involves the construction of the air traffic control building, a fire building station, as well as the expansion of the existing runway pavement. The construction of the fuel farm is to be funded by GOIL.

With the project being constructed by Messrs. Contracta Construction UK Limited, the total project sum is €124.9 million, with financing from Santander, Deutche Bank, and UKEF.

President Akufo-Addo expressed satisfaction with the progress of work undertaken so far, and charged the Ministry of Transport as well as the Contractor to ensure that the October 2022 deadline for completion is met.
Latest Stories
-
Hawa Koomson pledges experienced and mature leadership of NPP women’s wing
41 minutes -
Young woman found dead at Kasoa Peace Town
1 hour -
Playback: The Law examined lawful arrest in Ghana
2 hours -
Mahama urges African governments to treat healthcare as an investment, not budget cost
2 hours -
Bawumia congratulates John Boadu and new NPP executives, pledges support ahead of 2028
2 hours -
‘No talent should be left out’ – Bawumia pledges inclusive NPP campaign for 2028
2 hours -
Prof. Mike Oquaye recounts how he blocked the Special Prosecutor’s attempt to arrest Bawku Central MP
3 hours -
Make health sovereignty a priority for Africa – Mahama
3 hours -
Dorimon Naa, Wa West DCE lead massive clean-up exercise; threaten sanctions against recalcitrant residents
3 hours -
Photos from Adom FM Y2K Jam
3 hours -
Praye Tiatia steals the show at Adom FM Y2K Jam [Watch]
3 hours -
Boakye Agyarko congratulates John Boadu, pledges support for NPP leadership
3 hours -
Antwi HiMight thrills fans with Antwi ne Antwi hits at Adom FM’s Y2K Jam [Video]
4 hours -
Amb. Edward Boateng congratulates Boadu, Kodua on election wins
4 hours -
John Boadu pledges to rebuild NPP from grassroots and restore ‘winning machinery’
4 hours