A London-based arbitration tribunal has ruled in favour of the Electricity Company of Ghana (ECG), substantially rejecting the claim by Power Distribution Services Ghana Ltd. (PDS) for compensation following the termination of its management contract with ECG.
The tribunal’s ruling comes after nearly three years of proceedings and marks a decisive end to the long-running dispute stemming from the contract termination.
Under PDS’s claim, which reportedly totalled around US$390 million, the company alleged wrongful termination and sought to recover damages. The tribunal, however, found in favour of ECG and dismissed PDS’s claims.
PDS, in its initial response, acknowledged the ruling, calling it “respectful of the integrity of the arbitration process” and noting that its legal team is currently reviewing the decision in detail to determine the next steps.
ECG and the Government of Ghana, by extension, have welcomed the outcome as a vindication of the country’s oversight mechanisms in the power sector.
Latest Stories
-
Government secures 120 job opportunities for Ghanaians evacuated from South Africa
2 minutes -
Road Safety Authority urges caution as rains increase crash risks
4 minutes -
Nigeria’s Obi to run for president again after opposition split
5 minutes -
Mahama hails economic recovery, inflation drop and rising investor confidence in UK
10 minutes -
Mahama calls for a deeper Ghana–UK partnership beyond traditional trade
17 minutes -
Opposition parties call Ethiopia’s 7th election peaceful, free and participatory
22 minutes -
Minority alleges anti-LGBTQ bill was diluted through extensive amendments
29 minutes -
Anti-LGBTQ+Bill contains dozens of changes, but not weaker than the first — Barker-Vormawor
33 minutes -
Egypt’s long wait: Mohamed Salah and the Pharaohs’ reckoning
39 minutes -
Do not phase out pesewa coins — CPP to Bank of Ghana
47 minutes -
We’ll return to the negotiation table, but accept nothing below 20% – Concerned Drivers Association
52 minutes -
Marriage needs two wings to fly
53 minutes -
GTEC flags 70 unrecognised institutions
60 minutes -
Let there be light: Jubilation in Wa West as Tindoma and Welteng communities are connected to national grid
1 hour -
Health Ministry, Parliament and UNPA wage war against silent epidemic of obstetric fistula
1 hour