Ghana has been experiencing Dumsor long before the recent gas supply challenges announced by WAPCo .
Credible data available, representing total system power generation at peak periods (10 pm), shows that Ghana has been experiencing power generation deficits throughout this year.
This was evident even before WAPCo's announcement, which is expected to further increase the generation deficits (more DUMSOR).
As of December 26, 2023, Ghana's system peak load stood at 3,618 MW, representing a 4.3% increase from the 2022 recorded peak demand. In 2024, system peak load is estimated to be 3,788 MW, reflecting a 4.7% increase from 2023 Energy commission report 2024. This means that, Ghanas peak demand is expected to be around 3788 MW. Therefore any power generation below 3788 MW will result in DUMSOR.
Power generation at 10:00 PM represents the peak system power generation and the 10:00 PM also represents the peak demand period of power. System peak power generation has an average value of 3188.12 MW (January to June 4th). Monthly averages at these time were January 2024 =3162.45 MW, February 2024 = 3276.00 MW, March 2024 = 3154.73 MW, April 2024 = 3199.50 MW, May 2024 = 3161.29 MW, and June 2024 = 3101.33 MW.
1. The system peak power generation represents power generated for both domestic usage and export.
2. The total demand peak also includes power demanded domestically and for export.
3. The average power generated at peak periods (10 pm) from January to June 4th, 2024, stands at 3188.12 MW. This figure is far below the peak demand for even 2023, recorded on December 26th, 2023, at 3618 MW, let alone meeting the peak demand projected at 3788 MW for 2024 based on the energy commissions report.
4. This means that from January to June 4th, 2024, Ghana has never been able to meet its peak demand where its power generated (supply) will meet the peak demand. There is a deficit in power generation between 429.88 MW and 599.88 MW when using the 2023 peak demand of 3618 MW or the projected peak demand of 3788 MW, respectively.
5. Therefore, a deficit in power generation of 600 MW is accounting for the DUMSOR. From January 2024 to June 4th, 2024, Ghana experiences DUMSOR of about 600 MW.
6. With the new development where WAPCo has announced a gas supply challenge, causing ECG and GRIDCo to issue a joint press release, th end effect is that Ghana will experience more DUMSOR, meaning there will be a deficit in power generation beyond 600 MW.
7. The other good news is that the thermal plants can operate on Light Crude Oil (LCO) or Heavy Fuel Oil (HFO). Apart from Sunon-Asogli Power (SAPP) and AMERI, which rely only on Natural Gas, the rest operate on either HFO, LCO, or LPG. Therefore, with proper financial capacity, Ghana should be able to generate enough power to meet its peak demand. Ghana has an installed generation capacity of 5,194 MW, excluding embedded generation, which correlates to a dependable capacity of 4,756 MW. This means that Ghana should be generating enough power to exceed its peak demand.
8. In conclusion, ECG and the government should not ascribe the DUMSOR to WAPCo's gas supply challenges because we have already been generating power at a deficit of 600 MW even though WAPCo's gas supply challenges will worsen the DUMSOR situation, but not when the majority of the thermal plants can operate on either HFO, LCO, or LPG in place of Natural Gas.
About the author: Xatse Derick Emmanuel is a Research and Policy Analyst at the Institute For Energy Security-IES.
Latest Stories
-
Say not to single life
4 minutes -
Accra Institute of Technology matriculates students for 2025/2026 academic year
9 minutes -
Foresters demand arrest and prosecution after violent attack on Babatokuma Forestry Commission checkpoint
12 minutes -
GoldBod, Armed Forces and Forestry Commission launch national land reclamation project
12 minutes -
Ghana Boundary Commission launches African Border Day activities with water project in Bawku West
21 minutes -
Mfantsiman Old Girls’ Association to hold nationwide health walk on June 27
22 minutes -
Ghana, Burkina Faso launch fresh push to reaffirm shared border
31 minutes -
Ghana urged to use data science, AI to solve Ghana’s perennial flooding problem
31 minutes -
Musk’s SpaceX buys AI coding start-up for $60bn days after IPO
41 minutes -
Sandy Asare celebrates God’s grace in new single ‘Ɛyɛ Awurade’
51 minutes -
NPP failed Afari Hospital project despite 8 years in power – Kennedy Agyapong
53 minutes -
Fidelity Bank donates GH¢1m to Black Stars World Cup Fund
58 minutes -
PURC, Works and Housing Ministry push major water sector reforms to improve service delivery
1 hour -
GAAMP inducts first members, pushes for higher standards in Ghana’s aesthetic industry
1 hour -
GES must prioritise safe school policies alongside sanctions – Child rights advocate
1 hour