Construction has resumed on the Dome-Berekusu-Kitaase road project after a temporary halt caused by Ghana's IMF bailout programme.
The 23-kilometer stretch aims to connect the Greater Accra Region with the Eastern Region, serving as a crucial link for regional connectivity and economic development.
Originally budgeted at GH¢195 million, the project is jointly financed by the Kuwait Fund for Arab Economic Development (KFAED) and the Government of Ghana.
Groundbreaking took place in July 2022, with an initial completion target set for 24 months.
However, the country's IMF bailout and subsequent debt restructuring necessitated a suspension of the project, impacting road users and local commuters.
Residents have expressed relief at the project's restart but have also emphasised the urgency of its completion.
The road's deteriorated state has posed health and economic challenges, prompting calls for expedited construction to alleviate these hardships.
Concerns from commuters highlight issues such as the road's uneven surface and inadequate drainage, which have contributed to health risks and transportation difficulties.
Nicholas Tieku, the project site engineer, confirmed the availability of funding from the construction firm, enabling the resumption of work.
He outlined revised timelines for completion and detailed the scope of ongoing and upcoming construction activities aimed at improving road conditions and ensuring sustainable infrastructure development.
Latest Stories
-
Bawku conflict: High Court demands State accountability over three-week detention of Alhaji Seidu Abagre
43 seconds -
Boakyewaa Glover: To be witnessed
1 minute -
Daily Insight for CEOs: The CEO’s role in driving leadership accountability early in the year
3 minutes -
Akosua Manu refutes Kennedy Agyapong; Bawumia campaigned for NPP in Adenta
22 minutes -
Government’s reset agenda will take time to materialise – Ho Central MP
22 minutes -
Police seize over 1,600 parcels of suspected narcotic drugs in major bust
25 minutes -
Miguel Ribeiro Fiifi Brandful
26 minutes -
Trade Minister storms Abossey Okai to enforce fair pricing ,curb middlemen exploitation
30 minutes -
Hopeson Adorye calls for firm action against GWCL over persistent water shortages
39 minutes -
Two burnt to death in fiery Offinso road accident
1 hour -
NPP flatly rejects Frimpong-Boateng’s claims, defends 2024 flagbearer vote
1 hour -
NPP initiates process to expel Prof Frimpong-Boateng over “fake party” comments
1 hour -
Family of late Sawla-Tuna-Kalba MP appeals to President Mahama over GH¢944,955 demand blocking his burial
2 hours -
Today’s Front pages: Tuesday, January 13, 2026
3 hours -
Galamsey fight: Western Regional Minister calls for real-time monitoring of water bodies
3 hours