Audio By Carbonatix
Ghana’s nuclear power project risks further delays as critical technical studies required for construction readiness remain unfunded, project officials have said.
The project is currently in Phase Two, described as the “construction readiness” stage, which requires major site-related technical studies before moving forward.
However, while operational and administrative budget from the Government, Volta River Authority, and Bui Power Authority existed to support the project, funding for key technical activities was not available, Dr Stephen Yamoah, the Executive Director, Nuclear Power Ghana, told the Ghana News Agency in an interview in Accra on Monday.
The two most urgent requirements, he said, were detailed site characterisation and environmental impact assessment, calling on the Government to intervene.
Dr Yamoah said the two were fundamental to completing the feasibility assessment and transitioning into construction of the nuclear power project.
“Without these, the project cannot progress beyond Phase Two. If we are unable to conduct the site characterisation and complete the key technical studies, we are not moving beyond Phase Two,” he indicated.
Dr Yamoah stressed the need for the procurement of environmental monitoring as well as oceanographic and marine equipment to collect site-specific data for plant design.
“However, procurement processes cannot begin without budgetary allocation,” he explained, adding that a detailed grid impact study was expected to be undertaken this year.
The grid impact study, he noted, would assess the capacity of Ghana’s transmission system, the required upgrades to transmission lines, construction of new substations and safety systems needed to accommodate nuclear power plant.
He recalled that same funding gap mirrored challenges experienced during Phase One (1), which was originally expected to be completed in 2017 but was finalised in 2019 after delayed government releases for key technical studies.
He cautioned that prolonged delays could lead to public disinterest, community frustration and political fatigue.
Stakeholder engagement efforts are ongoing, but officials caution that without visible progress, momentum could wane.
Already, Ghana has made political commitments to include nuclear power to its energy mix to reduce reliance on fossil fuels, mitigate climate change, and enhance energy security.
In 2021 and 2023 Ghana issued a request for information and a follow up to vendors to partner the country in its quest to embark on the nuclear power project.
The vendor selection followed a thorough process, starting with a review of 15 responses to the government’s call.
A technical team, guided by the Energy Ministry, shortlisted five before choosing the final two.
The plant will support industrialisation, compensate for declining hydro sources, lower tariffs for industries, and create jobs.
Ghana’s nuclear ambition, disrupted by a coup in the 1960s, was revived in 2008 and has since received International Atomic Energy Agency (IAEA) technical support.
It is among several African countries pursuing nuclear energy to tackle power challenges and drive economic growth.
Latest Stories
-
‘This protocol nonsense into security services must stop’ – Senyo Hosi
20 seconds -
Overwhelming security recruitment applications pose national risk – Senyo Hosi
20 minutes -
Security Recruitment: Charging for forms unnecessary, says Kofi Bentil
32 minutes -
Financial clearance secured for nearly 15,000 rotation nurses, midwives and medical house officers
39 minutes -
Kumasi City Marathon 2026: A historic run through the heart of Ghana
44 minutes -
5,000 security services openings already filled through influence – Kofi Bentil alleges
1 hour -
Ex-deputy trade minister rejects ‘fictitious’ GH¢89.4m debt claim under 1D1F audit
1 hour -
GH¢21bn audit exposé reveals our governance system is designed to loot the state – Senyo Hosi
1 hour -
GH¢21bn Audit: We focus too much on politicians and ignore civil servants – Kofi Bentil
2 hours -
2026 World Cup: GHANSU to unveil sponsors and partners ahead of tournament
2 hours -
Gov’t using GH¢21bn audit narrative to divert attention from pressing issues – Okyere Baafi
2 hours -
Senyo Hosi backs Ato Forson’s GH¢21bn public claims audit
2 hours -
The BAC Group begins global engagement tour with visit to Issahaku ahead of All Star Festival 2026
2 hours -
GH¢21bn audit exposé: This is all for PR to deflect attention from pressing issues – Egyapa Mercer
2 hours -
GH¢21bn audit exposé: Some people must be prosecuted and jailed if found guilty – Joe Jackson
2 hours
