Audio By Carbonatix
Construction of the Wa Court Complex, which started 26 years ago to ease overcrowding in Upper West’s courts, remains incomplete, with litigants still squeezed into cramped courtrooms.
Members of Parliament’s Judiciary Committee, who inspected the site on Monday, said the project did not reflect the contractor’s claim of being 90% complete.

The committee described the state of work as unsatisfactory and said it would summon the contractor, Project Seven Limited, to appear before Parliament when it resumes.
The multimillion-cedi complex is designed to house three high and circuit courtrooms and offices for judicial staff. It was intended to replace inadequate facilities in Wa, where judges, lawyers, and litigants have operated in congested rooms for three decades. Court clerks have at times had to call cases from outside due to limited space.

Work on the project has stalled repeatedly since it began. At one point, then-Chief Justice Sophia Akuffo visited the site, confirmed the structure was sound, and ordered work to resume.
The contractor later abandoned the site, citing unpaid bills. The unfinished building became overgrown with weeds and was reportedly used as a pen for livestock and a hideout for suspected criminals.
Frustrated by the delays, authorities terminated the contract and awarded it to Project Seven Limited.

Work restarted a few years ago with the aim of commissioning the complex during the 2025 Ghana Bar Conference in Wa. That deadline was missed. During last Monday’s inspection, led by consultant Sylvester Dery of North West Consortium Limited, committee members said the level of work on site did not match the contractor’s 90% claim.
The structure, they said, was not disability-friendly. Committee Chairman and MP for Nkawkaw, Joseph Frimpong, expressed frustration over the pace of work.
"I am highly disappointed because what we were told in Accra is not what we are seeing here. We were told the work was done 90 per cent since December last year, and we are in the 5th month, and look at the state of the building," a visibly angered chairman stated.

Ranking member and MP for Lawra, Bede Ziedeng, echoed the concerns.
"The contractor complains of the delay in paying his outstanding certificates, assuring that once they are paid, it will give liquidity to the contractor to enable him to complete the work. After the payment of the outstanding certificates, we expected to come and see the work completed. We were coming to see, in addition to what had been done before. However, he came to complain to us after payment," he indicated.

MP for Zabzugu, Umar Alhassan, expressed frustration over the development.
"The disappointment is that the contractor is not here; he has pocketed his money, but the work remains. We will deal with him when we get to Accra," the Zabzugu MP vowed.
The chairman of the committee, Joseph Frimpong, added, “We will haul the contractor before the committee when Parliament resumes to explain this delay."



Latest Stories
-
24-Hour Economy targets greenhouses, cold storage and air cargo to transform horticulture
10 minutes -
Taxpayers’ money shouldn’t fund National Cathedral; Christians can contribute towards it – Mahama
21 minutes -
U.S. Embassy launches Girls’ soccer initiative in Ghana to build leaders on and off the pitch
26 minutes -
HIDAH Foundation equips youth with future-ready skills at free 2-day development programme
30 minutes -
Mahama: 24-Hour Markets will boost economic activity across districts
32 minutes -
Ablakwa celebrates PRESEC’s 9th NSMQ triumph, rewards contestants, staff with MacBooks and cash
45 minutes -
Free Primary Healthcare targets most deprived districts – GHS Director General
51 minutes -
Gov’t unveils ambitious cut-flower export corridor from from Daboya to Europe, West Africa and Gulf
1 hour -
‘Life Is Short’ gospel music hitmaker Bernice Offei dies at 63
2 hours -
Ghana’s economy has moved from standing on broomsticks to concrete pillars – Mahama
2 hours -
Systemic vulnerabilities within banking industry remain broadly subdued- BoG
2 hours -
Ghana, Côte d’Ivoire’s export sectors face heightened risks due to El l Niño – Fitch Solutions
2 hours -
Norway’s Princess Astrid dies two days after attending brother King Harald’s funeral
2 hours -
NCA awards 700MHz spectrum to MTN Ghana for US$109.9m
2 hours -
Saudi Arabia shuts key oil pipeline after drone attack launched from Iraq
2 hours